✅ Project Closeout Checklist

A comprehensive checklist to ensure nothing is missed during project closeout.

Why Use a Closeout Checklist?

Project closeout is where money goes to die. Incomplete closeout means:

  • Retainage held indefinitely
  • Final payment delayed
  • Warranty disputes
  • Unhappy clients (no referrals)

This checklist ensures you collect what you're owed and leave a good impression.


Phase 1: Pre-Closeout (30 Days Before Substantial Completion)

Administrative

  • Review contract for closeout requirements
  • Identify all required closeout documents
  • Request closeout submittals from subcontractors
  • Schedule pre-final inspection with owner/architect
  • Compile as-built drawings
  • Gather all warranties and guarantees
  • Prepare operation & maintenance manuals

Financial

  • Review all outstanding change orders — get signed
  • Identify unbilled work — submit final pay apps
  • Calculate final contract value
  • Review T&M work — ensure documented
  • Reconcile job costs vs. budget
  • Identify any backcharges to issue/resolve

Subcontractor Coordination

  • Issue punch list requirements to subs
  • Collect lien waivers (conditional) from subs
  • Verify sub insurance certificates current
  • Confirm sub warranty documents received
  • Schedule sub participation in commissioning

Phase 2: Substantial Completion

Punch List

  • Schedule punch list walkthrough with owner/architect
  • Complete punch list documentation
  • Issue punch list items to responsible parties
  • Set deadline for punch completion
  • Track punch list progress daily
  • Verify completed items
  • Final punch walkthrough — get sign-off

Inspections & Approvals

  • Final building inspection — obtain CO
  • Fire marshal inspection (if required)
  • Health department inspection (if required)
  • Elevator inspection (if applicable)
  • ADA compliance verification
  • Environmental closeout (if required)
  • LEED documentation (if applicable)

Testing & Commissioning

  • HVAC testing, adjusting, balancing (TAB)
  • Plumbing pressure tests
  • Electrical testing and panel schedules
  • Fire alarm testing
  • Fire sprinkler testing
  • Security system testing
  • Building automation verification
  • Generator/emergency power test

Phase 3: Documentation Package

As-Builts & Record Documents

  • Marked-up drawing sets collected from field
  • As-built drawings prepared (CAD/PDF)
  • Specification changes documented
  • RFI log — final version
  • Change order log — final version
  • Submittal log — final version

Operation & Maintenance Manuals

  • Equipment O&M manuals
  • Product data sheets
  • Warranty information
  • Spare parts lists
  • Maintenance schedules
  • Emergency contact list
  • System diagrams and schematics

Warranties & Guarantees

  • Contractor general warranty letter
  • Roofing warranty (often separate/extended)
  • HVAC equipment warranties
  • Manufacturer warranties compiled
  • Subcontractor warranties
  • Extended warranties (if purchased)

Certifications & Test Reports

  • Concrete test reports
  • Steel certifications
  • Soil compaction reports
  • Special inspection reports
  • HVAC TAB report
  • Commissioning report
  • Fire protection certifications

Phase 4: Training & Turnover

Owner Training

  • HVAC system operation
  • Building automation/controls
  • Fire/life safety systems
  • Security system
  • Plumbing systems (if complex)
  • Electrical systems (generators, etc.)
  • Landscape/irrigation (if applicable)

Training Documentation

  • Sign-in sheets for all training sessions
  • Video recordings (if required)
  • Quick reference guides provided
  • Emergency procedures reviewed
  • Maintenance schedule explained
  • Warranty claim procedures explained

Keys & Access

  • Final keying complete
  • Key schedule/bitting chart
  • Keys turned over to owner
  • Access cards/fobs programmed
  • Master key documentation
  • Security codes transferred

Phase 5: Financial Closeout

Pay Applications

  • Submit final pay application
  • Include all completed change orders
  • Attach required lien waivers
  • Submit retainage release request
  • Verify stored materials billed
  • Reconcile all billings

Lien Waivers

  • Conditional final waiver submitted (with final pay app)
  • Subcontractor conditional finals collected
  • Upon payment: Unconditional final waiver
  • Subcontractor unconditional finals collected
  • Supplier unconditional finals collected

Cost Reconciliation

  • Final job cost report completed
  • Compare budget vs. actual
  • Document lessons learned
  • Calculate final profit/loss
  • Close out job in accounting system
  • Archive financial records

Phase 6: Site Closeout

Demobilization

  • Remove temporary facilities (trailer, etc.)
  • Remove temporary utilities
  • Remove temporary fencing
  • Remove all equipment from site
  • Clean up storage/laydown areas
  • Return rented equipment

Final Cleanup

  • Construction debris removed
  • Interior cleaning complete
  • Window cleaning complete
  • Final vacuum/mop
  • Exterior cleanup complete
  • Landscaping areas cleaned

Site Restoration

  • Paving/striping complete
  • Landscaping installed/complete
  • Irrigation operational
  • Signage installed
  • Site lighting operational
  • Fencing/gates operational

Phase 7: Project Archive

Documentation Archive

  • Contract documents archived
  • Drawings (original + as-built) archived
  • Specifications archived
  • Correspondence files archived
  • Meeting minutes archived
  • Photos organized and archived
  • Daily reports archived
  • Inspection reports archived

Financial Archive

  • Pay applications archived
  • Change orders archived
  • Lien waivers archived
  • Insurance certificates archived
  • Final cost report archived
  • Budget vs. actual archived

Digital Backup

  • All files backed up to server
  • Project management software data exported
  • Photos/videos backed up
  • Email correspondence saved
Retention Period

Keep project records for the duration of the warranty period PLUS the statute of limitations (often 4-10 years depending on state). When in doubt, keep it longer.


Closeout Transmittal Checklist

Use this when formally submitting closeout package:

CLOSEOUT TRANSMITTAL

Project: _________________________________
Date: ____________________________________
Submitted By: ____________________________

Enclosed documents:
□ Certificate of Substantial Completion
□ Certificate of Occupancy (copy)
□ As-Built Drawings (__ sets)
□ O&M Manuals (__ volumes)
□ Warranty Compilation
□ Training Sign-off Sheets
□ Final Lien Waivers
□ Final Pay Application
□ Keys and Key Schedule
□ Spare Parts and Attic Stock
□ Other: _______________________

By signing below, Owner acknowledges receipt of the above:

_____________________ ___________
Owner Signature Date

Common Closeout Problems

ProblemPrevention
Missing submittalsTrack from day one, not closeout
Sub won't provide waiverWithhold their final payment
Punch list drags onSet hard deadlines with consequences
Missing warrantiesRequire before final payment
O&M manuals incompleteSpec requirements clearly upfront
Retainage heldFollow up weekly, escalate
No CO issuedTrack inspection schedule early
Start Early

Closeout starts at project kickoff, not substantial completion. Track submittals, warranties, and O&M requirements from day one.