โ Project Startup Checklist
A comprehensive checklist to ensure your project starts right. Good project startup prevents problems during construction and closeout.
Why Project Startup Mattersโ
Starting a project well prevents:
- Payment problems (missing notices, wrong paperwork)
- Schedule delays (permits, submittals, long-lead items)
- Cost overruns (missed scope, bad estimates)
- Relationship damage (miscommunication, unclear expectations)
The First 30 Days
The first 30 days set the tone for the entire project. Invest time upfront to avoid problems later.
Phase 1: Pre-Construction (Before Mobilization)โ
Contract & Legalโ
- Signed contract received and reviewed
- Contract amount matches proposal/bid
- Scope of work clearly defined
- Exclusions documented
- Payment terms understood (retention, billing dates)
- Change order procedures defined
- Insurance requirements identified
- Bond requirements identified (if any)
- Indemnification clauses reviewed by counsel
- Warranty terms understood
Lien Rights Protectionโ
- Preliminary notice sent (if required by state)
- Lien deadline calendar created
- Property owner information verified
- GC/lender information documented
- Notice requirements for each tier understood
Insurance & Bondingโ
- Insurance certificates sent to GC/owner
- COI names additional insureds correctly
- Workers' comp certificate provided
- Auto insurance certificate provided
- Excess/umbrella coverage confirmed
- Bonds ordered (if required)
- Bond forms match contract requirements
Project Team Setupโ
- Project manager assigned
- Superintendent assigned
- Project engineer assigned (if applicable)
- Key contacts list created
- Emergency contact list created
- Communication protocols established
- Reporting requirements understood
Phase 2: Project Setup (Week 1)โ
Administrative Setupโ
- Job number created in accounting system
- Project folder/file structure created
- Document control system set up
- Drawing log started
- RFI log created
- Submittal log created
- Change order log created
- Daily report template ready
Schedule of Valuesโ
- Schedule of Values (SOV) prepared
- SOV submitted for approval
- Line items match contract scope
- Appropriate level of detail
- Change order provisions included
- Billing format approved
Budget Setupโ
- Project budget created
- Cost codes assigned
- Labor budget by phase
- Material budget by category
- Subcontract values entered
- Equipment budget established
- Contingency allocated
- Profit margin identified
Subcontractor Coordinationโ
- Subcontracts issued
- Subcontractor insurance received
- Subcontractor licenses verified
- Scope letters/exhibits attached
- Payment terms communicated
- Scheduling requirements communicated
- Safety requirements communicated
Phase 3: Document Review (Week 1-2)โ
Drawings Reviewโ
- All drawing sheets received
- Latest revision confirmed
- Drawing log created with issue dates
- Architectural drawings reviewed
- Structural drawings reviewed
- MEP drawings reviewed
- Civil/site drawings reviewed
- Conflicts/issues noted
Specifications Reviewโ
- All specification sections received
- Submittal requirements extracted
- Product substitutions identified
- Quality requirements noted
- Testing requirements identified
- Closeout requirements noted
Existing Conditionsโ
- Site visit completed
- Existing conditions documented (photos)
- Access routes confirmed
- Utility locations identified
- Adjacent property conditions documented
- Pre-construction survey (if needed)
Phase 4: Submittals & Long-Lead Items (Week 1-2)โ
Submittal Scheduleโ
- Submittal log created from specs
- Long-lead items identified
- Submittal schedule created
- Submittal responsibilities assigned
- Review times built into schedule
Long-Lead Items Orderedโ
Priority items to release immediately:
- Structural steel
- Elevators
- Electrical switchgear
- Generators
- Mechanical equipment
- Custom millwork
- Specialty doors/hardware
- Custom light fixtures
- Curtain wall systems
Product Selectionsโ
- Owner selections complete
- Allowance items identified
- Substitutions approved
- Color/finish selections made
- Samples submitted/approved
Phase 5: Site Mobilizationโ
Permits & Approvalsโ
- Building permit obtained
- Demolition permit (if needed)
- Grading permit (if needed)
- Street/sidewalk permit (if needed)
- Utility connection permits
- Fire department approval
- SWPPP/erosion control plan (if needed)
Site Setupโ
- Site access established
- Temporary fencing installed
- Project signage posted
- Office trailer delivered/setup
- Temporary power established
- Temporary water established
- Temporary toilets placed
- Dumpster/waste containers placed
- Tool storage secured
- Material laydown area designated
Safety Setupโ
- Site-specific safety plan created
- OSHA posting requirements met
- First aid kit on site
- Fire extinguishers placed
- Emergency numbers posted
- Safety orientation materials ready
- PPE requirements posted
- Jobsite safety rules posted
Phase 6: Kickoff Meetingโ
Internal Kickoffโ
Hold with your team before owner kickoff:
- Project scope reviewed
- Schedule reviewed
- Budget reviewed
- Team roles clarified
- Risk areas discussed
- Quality standards established
- Communication plan confirmed
- Questions answered
Owner/GC Kickoff Meetingโ
Agenda items to cover:
- Introductions and roles
- Project scope confirmation
- Schedule review and milestones
- Communication protocols
- Meeting schedule established
- RFI/submittal procedures
- Change order procedures
- Pay application procedures
- Site access and logistics
- Safety requirements
- Quality expectations
- Closeout requirements preview
Meeting Documentationโ
- Meeting minutes distributed
- Action items assigned
- Decisions documented
- Open issues tracked
Phase 7: Schedule Developmentโ
Master Scheduleโ
- Master schedule developed
- Milestones identified
- Critical path identified
- Subcontractor input obtained
- Owner approval received
- Schedule distributed to team
Look-Ahead Scheduleโ
- 3-week look-ahead created
- Updated weekly
- Distributed at OAC meetings
Key Dates Trackedโ
- Substantial completion date
- Final completion date
- Liquidated damages trigger
- Owner move-in date
- Permit expiration dates
- Inspection milestones
Phase 8: Communication Setupโ
Meetings Scheduledโ
- OAC meeting schedule (weekly/biweekly)
- Foreman meeting schedule
- Safety meeting schedule
- Subcontractor coordination meetings
Technology Setupโ
- Project management software access
- Drawing viewer/BIM access
- File sharing access
- Team email list created
- Photo documentation system
Reporting Scheduleโ
- Daily report procedures
- Weekly progress report format
- Monthly progress photos
- Pay application schedule
Common Startup Mistakes to Avoidโ
| Mistake | Consequence | Prevention |
|---|---|---|
| Missing preliminary notice | Lost lien rights | Send day 1 |
| Not reviewing contract | Surprise terms | Review before signing |
| Late submittals | Schedule delay | Submit week 1 |
| No kickoff meeting | Miscommunication | Schedule before start |
| Skipping site survey | Unknown conditions | Document pre-construction |
| Wrong insurance | Coverage gaps | Verify requirements |
| No budget setup | Cost surprises | Set up before billing |
Startup Meeting Checklist (Quick Reference)โ
Print and bring to kickoff meeting:
โก Contract copy
โก Drawings (latest revision)
โก Specifications
โก Schedule
โก Schedule of Values
โก RFI log
โก Submittal schedule
โก Contact list
โก Safety plan
โก Meeting agenda
โก Note-taking materials