A comprehensive checklist to ensure your project starts right. Good project startup prevents problems during construction and closeout.


Why Project Startup Mattersโ€‹

Starting a project well prevents:

  • Payment problems (missing notices, wrong paperwork)
  • Schedule delays (permits, submittals, long-lead items)
  • Cost overruns (missed scope, bad estimates)
  • Relationship damage (miscommunication, unclear expectations)
The First 30 Days

The first 30 days set the tone for the entire project. Invest time upfront to avoid problems later.


Phase 1: Pre-Construction (Before Mobilization)โ€‹

  • Signed contract received and reviewed
  • Contract amount matches proposal/bid
  • Scope of work clearly defined
  • Exclusions documented
  • Payment terms understood (retention, billing dates)
  • Change order procedures defined
  • Insurance requirements identified
  • Bond requirements identified (if any)
  • Indemnification clauses reviewed by counsel
  • Warranty terms understood

Lien Rights Protectionโ€‹

  • Preliminary notice sent (if required by state)
  • Lien deadline calendar created
  • Property owner information verified
  • GC/lender information documented
  • Notice requirements for each tier understood

Insurance & Bondingโ€‹

  • Insurance certificates sent to GC/owner
  • COI names additional insureds correctly
  • Workers' comp certificate provided
  • Auto insurance certificate provided
  • Excess/umbrella coverage confirmed
  • Bonds ordered (if required)
  • Bond forms match contract requirements

Project Team Setupโ€‹

  • Project manager assigned
  • Superintendent assigned
  • Project engineer assigned (if applicable)
  • Key contacts list created
  • Emergency contact list created
  • Communication protocols established
  • Reporting requirements understood

Phase 2: Project Setup (Week 1)โ€‹

Administrative Setupโ€‹

  • Job number created in accounting system
  • Project folder/file structure created
  • Document control system set up
  • Drawing log started
  • RFI log created
  • Submittal log created
  • Change order log created
  • Daily report template ready

Schedule of Valuesโ€‹

  • Schedule of Values (SOV) prepared
  • SOV submitted for approval
  • Line items match contract scope
  • Appropriate level of detail
  • Change order provisions included
  • Billing format approved

Budget Setupโ€‹

  • Project budget created
  • Cost codes assigned
  • Labor budget by phase
  • Material budget by category
  • Subcontract values entered
  • Equipment budget established
  • Contingency allocated
  • Profit margin identified

Subcontractor Coordinationโ€‹

  • Subcontracts issued
  • Subcontractor insurance received
  • Subcontractor licenses verified
  • Scope letters/exhibits attached
  • Payment terms communicated
  • Scheduling requirements communicated
  • Safety requirements communicated

Phase 3: Document Review (Week 1-2)โ€‹

Drawings Reviewโ€‹

  • All drawing sheets received
  • Latest revision confirmed
  • Drawing log created with issue dates
  • Architectural drawings reviewed
  • Structural drawings reviewed
  • MEP drawings reviewed
  • Civil/site drawings reviewed
  • Conflicts/issues noted

Specifications Reviewโ€‹

  • All specification sections received
  • Submittal requirements extracted
  • Product substitutions identified
  • Quality requirements noted
  • Testing requirements identified
  • Closeout requirements noted

Existing Conditionsโ€‹

  • Site visit completed
  • Existing conditions documented (photos)
  • Access routes confirmed
  • Utility locations identified
  • Adjacent property conditions documented
  • Pre-construction survey (if needed)

Phase 4: Submittals & Long-Lead Items (Week 1-2)โ€‹

Submittal Scheduleโ€‹

  • Submittal log created from specs
  • Long-lead items identified
  • Submittal schedule created
  • Submittal responsibilities assigned
  • Review times built into schedule

Long-Lead Items Orderedโ€‹

Priority items to release immediately:

  • Structural steel
  • Elevators
  • Electrical switchgear
  • Generators
  • Mechanical equipment
  • Custom millwork
  • Specialty doors/hardware
  • Custom light fixtures
  • Curtain wall systems

Product Selectionsโ€‹

  • Owner selections complete
  • Allowance items identified
  • Substitutions approved
  • Color/finish selections made
  • Samples submitted/approved

Phase 5: Site Mobilizationโ€‹

Permits & Approvalsโ€‹

  • Building permit obtained
  • Demolition permit (if needed)
  • Grading permit (if needed)
  • Street/sidewalk permit (if needed)
  • Utility connection permits
  • Fire department approval
  • SWPPP/erosion control plan (if needed)

Site Setupโ€‹

  • Site access established
  • Temporary fencing installed
  • Project signage posted
  • Office trailer delivered/setup
  • Temporary power established
  • Temporary water established
  • Temporary toilets placed
  • Dumpster/waste containers placed
  • Tool storage secured
  • Material laydown area designated

Safety Setupโ€‹

  • Site-specific safety plan created
  • OSHA posting requirements met
  • First aid kit on site
  • Fire extinguishers placed
  • Emergency numbers posted
  • Safety orientation materials ready
  • PPE requirements posted
  • Jobsite safety rules posted

Phase 6: Kickoff Meetingโ€‹

Internal Kickoffโ€‹

Hold with your team before owner kickoff:

  • Project scope reviewed
  • Schedule reviewed
  • Budget reviewed
  • Team roles clarified
  • Risk areas discussed
  • Quality standards established
  • Communication plan confirmed
  • Questions answered

Owner/GC Kickoff Meetingโ€‹

Agenda items to cover:

  • Introductions and roles
  • Project scope confirmation
  • Schedule review and milestones
  • Communication protocols
  • Meeting schedule established
  • RFI/submittal procedures
  • Change order procedures
  • Pay application procedures
  • Site access and logistics
  • Safety requirements
  • Quality expectations
  • Closeout requirements preview

Meeting Documentationโ€‹

  • Meeting minutes distributed
  • Action items assigned
  • Decisions documented
  • Open issues tracked

Phase 7: Schedule Developmentโ€‹

Master Scheduleโ€‹

  • Master schedule developed
  • Milestones identified
  • Critical path identified
  • Subcontractor input obtained
  • Owner approval received
  • Schedule distributed to team

Look-Ahead Scheduleโ€‹

  • 3-week look-ahead created
  • Updated weekly
  • Distributed at OAC meetings

Key Dates Trackedโ€‹

  • Substantial completion date
  • Final completion date
  • Liquidated damages trigger
  • Owner move-in date
  • Permit expiration dates
  • Inspection milestones

Phase 8: Communication Setupโ€‹

Meetings Scheduledโ€‹

  • OAC meeting schedule (weekly/biweekly)
  • Foreman meeting schedule
  • Safety meeting schedule
  • Subcontractor coordination meetings

Technology Setupโ€‹

  • Project management software access
  • Drawing viewer/BIM access
  • File sharing access
  • Team email list created
  • Photo documentation system

Reporting Scheduleโ€‹

  • Daily report procedures
  • Weekly progress report format
  • Monthly progress photos
  • Pay application schedule

Common Startup Mistakes to Avoidโ€‹

MistakeConsequencePrevention
Missing preliminary noticeLost lien rightsSend day 1
Not reviewing contractSurprise termsReview before signing
Late submittalsSchedule delaySubmit week 1
No kickoff meetingMiscommunicationSchedule before start
Skipping site surveyUnknown conditionsDocument pre-construction
Wrong insuranceCoverage gapsVerify requirements
No budget setupCost surprisesSet up before billing

Startup Meeting Checklist (Quick Reference)โ€‹

Print and bring to kickoff meeting:

โ–ก Contract copy
โ–ก Drawings (latest revision)
โ–ก Specifications
โ–ก Schedule
โ–ก Schedule of Values
โ–ก RFI log
โ–ก Submittal schedule
โ–ก Contact list
โ–ก Safety plan
โ–ก Meeting agenda
โ–ก Note-taking materials