📅 Lien Deadline Calculator

Calculate California mechanics lien deadlines. Know when to send prelim notices, file liens, and foreclose.

California Deadlines Quick Reference

DocumentDeadline
Preliminary Notice20 days from first furnishing
Mechanics Lien (with NOC)GC: 60 days / Sub: 30 days
Mechanics Lien (no NOC)90 days from completion
Foreclosure Lawsuit90 days from recording lien

How to Calculate Your Deadlines

Step 1: When Did You Start?

Your first day furnishing labor, materials, or equipment to the project.

Step 2: Did the Owner File a NOC?

Check with the county recorder. A Notice of Completion shortens your deadlines.

Step 3: Calculate Your Dates

If NO Notice of Completion:

  • Prelim: First furnish date + 20 days
  • Lien: Completion date + 90 days
  • Foreclose: Lien recording + 90 days

If Notice of Completion WAS filed:

  • Prelim: First furnish date + 20 days
  • Lien (GC): NOC recording + 60 days
  • Lien (Sub): NOC recording + 30 days
  • Foreclose: Lien recording + 90 days
Deadlines Are Strict

California courts rarely grant extensions. If you're close to a deadline, file immediately.

Interactive Calculator

First day you furnished labor, materials, or equipment