Skip to main content
Skip to main content

๐Ÿ’ต Retainage Guide

Retainage (retention) is money that's rightfully yours โ€” held until project completion. Here's how to manage it and get paid.

Retainage release process
1
Track retainage throughout project
Maintain a running retainage log by pay period. Know exactly how much is held and by whom โ€” GC, owner, and each sub.
2
Achieve substantial completion
Reach the contractual definition of substantial completion. Get the architect's certificate or owner's written acknowledgment.
3
Complete punch list items
Finish all punch list work promptly. Incomplete items give the owner a reason to withhold beyond the contract terms.
4
Submit retainage release request
Send a formal request with lien waivers, warranty letters, O&M manuals, and all required closeout documents.
5
Follow up and collect
Track the release through approval. If withheld beyond contract terms, assert your rights โ€” retainage has statutory release deadlines in many states.

What is Retainage?โ€‹

Retainage is a percentage of each progress payment withheld by the owner (and passed down to subs) until project completion.

Purpose: Ensure contractors complete their work and address punch list items.

Typical rates:

  • Private work: 5-10%
  • Public work: 5% (often capped by law)
  • California public: 5% maximum by law

The Cash Flow Impactโ€‹

On a $1M subcontract with 10% retention:

  • You earn $100,000 that you don't receive
  • For 12-18 months (typical project duration)
  • That's your profit margin held hostage
Contract ValueRetention %Retained Amount
$500,0005%$25,000
$500,00010%$50,000
$1,000,0005%$50,000
$1,000,00010%$100,000

State Laws on Retainageโ€‹

Californiaโ€‹

  • Public works: Maximum 5%
  • Private works: No statutory limit (negotiate)
  • Release to subs: Within 7 days of owner payment to GC
  • Interest: 2% per month if late (public)

Other States with Limitsโ€‹

StatePublicPrivate
Texas10%10%
Florida10% โ†’ 5% at 50%10%
New York5%No limit
Arizona10%No limit
Colorado5%No limit

Check your state โ€” rules vary significantly.

When is Retention Released?โ€‹

Typical Milestonesโ€‹

MilestoneRelease
Substantial completion50% release (sometimes)
Final completionRemaining balance
Warranty period endSometimes held longer

Subcontractor vs Primeโ€‹

For subs: Retention should be released when:

  • Your scope is complete and accepted
  • Punch list items are resolved
  • Required documentation submitted

Don't let GCs hold your retention until their entire project is complete if your work was accepted earlier.

Getting Your Retention Releasedโ€‹

1. Know Your Contractโ€‹

Look for:

  • Retention percentage
  • Release milestones
  • Time limits for release
  • Documentation requirements
  • Interest on late payment

2. Document Completionโ€‹

Before requesting release:

  • Scope of work complete
  • Punch list items resolved
  • As-built drawings submitted
  • O&M manuals delivered
  • Warranties provided
  • Final lien waiver ready

3. Submit Formal Requestโ€‹

Send written request including:

  • Project name and contract reference
  • Amount of retention held
  • Statement that work is complete
  • List of documentation provided
  • Request for payment within contract terms

4. Follow Upโ€‹

If no response:

  • Send reminder at contract deadline
  • Call project manager
  • Escalate to management
  • Note interest accruing (if applicable)
  • Consider lien rights (private work)

Retention Release Letter Templateโ€‹

[Your Company Letterhead]

Date: [Date]

To: [GC/Owner Name] [Address]

Re: Request for Retention Release Project: [Project Name] Contract: [Contract Number/Date]

Dear [Name]:

[Company Name] has completed all work under our contract for the above project. Our scope was accepted on [date], and all punch list items have been addressed.

We request release of retention in the amount of $[Amount].

Enclosed please find:

  • Final conditional lien waiver
  • Warranty documentation
  • As-built drawings
  • O&M manuals

Per our contract, retention is due within [X] days of substantial completion. Please remit payment by [date].

Thank you for your prompt attention.

Sincerely, [Signature] [Name, Title]

If They Won't Payโ€‹

Step 1: Demand Letterโ€‹

Send formal demand with:

  • Specific amount owed
  • Contract reference
  • Deadline for payment
  • Statement of intent to pursue remedies

Step 2: Preserve Lien Rightsโ€‹

On private work:

  • File mechanics lien before deadline
  • Retention is lienable

Options include:

  • Small claims court (if under limit)
  • Breach of contract lawsuit
  • Payment bond claim (if bonded)

Negotiating Better Termsโ€‹

At Contract Signingโ€‹

Ask ForBenefit
5% instead of 10%Less cash tied up
Reduction at 50% completeEarlier partial release
Sub-specific releaseDon't wait for whole project
Interest on late releaseIncentive to pay
Retention bond optionReplace cash with bond

Retention Bondsโ€‹

A retention bond allows:

  • You receive retention payments as earned
  • Owner holds bond instead of cash
  • Bond cost: typically 1-2% of retention amount

Example:

  • Retention: $50,000
  • Bond cost: $500-1,000
  • You get $50,000 now instead of in 18 months
  • Worth it if you need the cash flow

Was this page helpful?