Skip to main content
Skip to main content

📑 Submittal Log Generator

Create and track construction submittals from preparation through approval. Includes status tracking with summary counts.

What is a Submittal?

A submittal is documentation submitted to the architect/engineer for review and approval before materials are fabricated or installed. Submittals verify that products meet contract requirements.


Interactive Generator

Submittal Log Generator

Project Information
Submittals
#001

Status Codes

CodeMeaningAction Required
PendingNot yet submittedPrepare submittal
SubmittedSent to A/EAwaiting review
ApprovedNo exceptionsProceed with work
Approved as NotedMinor commentsReview notes, proceed
Revise & ResubmitRejectedCorrect and resubmit
RejectedDoes not complyMajor revision needed
For Record OnlyNo review requiredFile in project records

Long-Lead Items

These items typically require early submittal:

ItemTypical Lead Time
Structural steel8-16 weeks
Elevators16-24 weeks
Electrical switchgear12-20 weeks
Generators10-16 weeks
Custom millwork8-12 weeks
Curtain wall12-20 weeks
Start Immediately

Long-lead submittals should be prepared in the first 2 weeks of a project. Late long-lead submittals are the #1 cause of schedule delays.