📑 Submittal Log Generator
Create and track construction submittals from preparation through approval. Includes status tracking with summary counts.
What is a Submittal?
A submittal is documentation submitted to the architect/engineer for review and approval before materials are fabricated or installed. Submittals verify that products meet contract requirements.
Interactive Generator
Status Codes
| Code | Meaning | Action Required |
|---|---|---|
| Pending | Not yet submitted | Prepare submittal |
| Submitted | Sent to A/E | Awaiting review |
| Approved | No exceptions | Proceed with work |
| Approved as Noted | Minor comments | Review notes, proceed |
| Revise & Resubmit | Rejected | Correct and resubmit |
| Rejected | Does not comply | Major revision needed |
| For Record Only | No review required | File in project records |
Long-Lead Items
These items typically require early submittal:
| Item | Typical Lead Time |
|---|---|
| Structural steel | 8-16 weeks |
| Elevators | 16-24 weeks |
| Electrical switchgear | 12-20 weeks |
| Generators | 10-16 weeks |
| Custom millwork | 8-12 weeks |
| Curtain wall | 12-20 weeks |
Start Immediately
Long-lead submittals should be prepared in the first 2 weeks of a project. Late long-lead submittals are the #1 cause of schedule delays.