Skip to main content
Skip to main content

Project Risk Management Procedure

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Estimating, Executives


Purpose

Establish procedures for identifying, assessing, and managing project risks.


Risk Management Process

Identify → Assess → Plan Response → Monitor → Update

Risk Categories

Schedule Risks:

  • Weather delays
  • Permitting delays
  • Long-lead items
  • Subcontractor availability
  • Inspections
  • Owner decisions

Cost Risks:

  • Material price escalation
  • Labor productivity
  • Scope creep
  • Change orders
  • Claims
  • Unforeseen conditions

Quality Risks:

  • Design errors
  • Workmanship issues
  • Material defects
  • Inspection failures

Safety Risks:

  • Site hazards
  • High-risk activities
  • Subcontractor safety culture

External Risks:

  • Regulatory changes
  • Market conditions
  • Weather/natural events
  • Supply chain
  • Economic conditions

Risk Identification

Sources:

  • Project documents review
  • Site investigation
  • Lessons learned (similar projects)
  • Team brainstorming
  • Subcontractor input
  • Owner discussions

Questions to Ask:

  • What could go wrong?
  • What has gone wrong before?
  • What is unique about this project?
  • What are the unknowns?
  • What depends on others?

Risk Assessment Matrix

Probability:

LevelDescriptionLikelihood
5Almost certainover 90%
4Likely60-90%
3Possible30-60%
2Unlikely10-30%
1Rareunder 10%

Impact:

LevelScheduleCostDescription
5over 2 monthsover 15%Critical
41-2 months10-15%Major
32-4 weeks5-10%Moderate
21-2 weeks2-5%Minor
1under 1 weekunder 2%Negligible

Risk Score:

Risk Score = Probability × Impact
ScoreRisk LevelAction
15-25CriticalImmediate attention
8-14HighActive management
4-7MediumMonitor closely
1-3LowAccept or monitor

Risk Register

================================================================
PROJECT RISK REGISTER
================================================================

Project: ___________________________________________________

Date: _____________________________________________________

================================================================

| ID | Risk Description | Category | Prob | Impact | Score | Response | Owner | Status |
|----|------------------|----------|------|--------|-------|----------|-------|--------|
| R1 | | | | | | | | |
| R2 | | | | | | | | |
| R3 | | | | | | | | |

================================================================

RESPONSE TYPES:
- Avoid: Eliminate the risk
- Mitigate: Reduce probability or impact
- Transfer: Insurance, subcontract
- Accept: Acknowledge and monitor

================================================================

Risk Response Strategies

Avoid:

  • Change approach
  • Eliminate cause
  • Different scope/method

Mitigate:

  • Early procurement
  • Additional resources
  • Contingency planning
  • Quality controls

Transfer:

  • Insurance
  • Subcontract (shifts to others)
  • Performance bonds
  • Contract terms

Accept:

  • Acknowledge risk exists
  • Budget contingency
  • Monitor for occurrence

Common Construction Risks and Responses

RiskResponse Options
Material escalationLock pricing early, allowances, escalation clause
WeatherSchedule buffer, weather contingency, covered work
Subsurface conditionsGeotechnical study, contingency, differing conditions clause
Permitting delaysEarly submittal, pre-application meetings, float
Design errorsRFI process, constructability review, contingency
Labor shortageEarly recruitment, pre-hire, multiple sources
Subcontractor defaultPrequalification, bonds, backup subs
Owner changesChange order process, document all directions

Risk Monitoring

Regular Reviews:

  • Weekly (active risks)
  • Monthly (all risks)
  • Major milestones
  • When conditions change

Track:

  • Risk status
  • New risks
  • Closed risks
  • Effectiveness of responses

Risk Contingency

Budget Contingency:

Risk LevelContingency
Low risk project2-3%
Medium risk5-7%
High risk8-10%+

Schedule Contingency:

  • Add float for high-risk activities
  • Buffer before milestones
  • Reasonable overall duration

Risk Communication

Communicate Risks To:

  • Project team
  • Management
  • Owner (as appropriate)
  • Subcontractors (their risks)

Risk Escalation:

  • Critical risks → Executive attention
  • Budget impacts → Finance
  • Schedule impacts → Operations

  • Bid Pursuit (Go/No-Go)
  • Estimating Standards
  • Change Order Management
  • Claims Procedures

Template provided by support.construction. Proactive risk management protects projects.