Skip to main content
Skip to main content

Project Risk Management Procedure

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Estimating, Executives


Purposeโ€‹

Establish procedures for identifying, assessing, and managing project risks.


Risk Management Processโ€‹

Identify โ†’ Assess โ†’ Plan Response โ†’ Monitor โ†’ Update

Risk Categoriesโ€‹

Schedule Risks:โ€‹

  • Weather delays
  • Permitting delays
  • Long-lead items
  • Subcontractor availability
  • Inspections
  • Owner decisions

Cost Risks:โ€‹

  • Material price escalation
  • Labor productivity
  • Scope creep
  • Change orders
  • Claims
  • Unforeseen conditions

Quality Risks:โ€‹

  • Design errors
  • Workmanship issues
  • Material defects
  • Inspection failures

Safety Risks:โ€‹

  • Site hazards
  • High-risk activities
  • Subcontractor safety culture

External Risks:โ€‹

  • Regulatory changes
  • Market conditions
  • Weather/natural events
  • Supply chain
  • Economic conditions

Risk Identificationโ€‹

Sources:โ€‹

  • Project documents review
  • Site investigation
  • Lessons learned (similar projects)
  • Team brainstorming
  • Subcontractor input
  • Owner discussions

Questions to Ask:โ€‹

  • What could go wrong?
  • What has gone wrong before?
  • What is unique about this project?
  • What are the unknowns?
  • What depends on others?

Risk Assessment Matrixโ€‹

Probability:โ€‹

LevelDescriptionLikelihood
5Almost certainover 90%
4Likely60-90%
3Possible30-60%
2Unlikely10-30%
1Rareunder 10%

Impact:โ€‹

LevelScheduleCostDescription
5over 2 monthsover 15%Critical
41-2 months10-15%Major
32-4 weeks5-10%Moderate
21-2 weeks2-5%Minor
1under 1 weekunder 2%Negligible

Risk Score:โ€‹

Risk Score = Probability ร— Impact
ScoreRisk LevelAction
15-25CriticalImmediate attention
8-14HighActive management
4-7MediumMonitor closely
1-3LowAccept or monitor

Risk Registerโ€‹

================================================================
PROJECT RISK REGISTER
================================================================

Project: ___________________________________________________

Date: _____________________________________________________

================================================================

| ID | Risk Description | Category | Prob | Impact | Score | Response | Owner | Status |
|----|------------------|----------|------|--------|-------|----------|-------|--------|
| R1 | | | | | | | | |
| R2 | | | | | | | | |
| R3 | | | | | | | | |

================================================================

RESPONSE TYPES:
- Avoid: Eliminate the risk
- Mitigate: Reduce probability or impact
- Transfer: Insurance, subcontract
- Accept: Acknowledge and monitor

================================================================

Risk Response Strategiesโ€‹

Avoid:โ€‹

  • Change approach
  • Eliminate cause
  • Different scope/method

Mitigate:โ€‹

  • Early procurement
  • Additional resources
  • Contingency planning
  • Quality controls

Transfer:โ€‹

  • Insurance
  • Subcontract (shifts to others)
  • Performance bonds
  • Contract terms

Accept:โ€‹

  • Acknowledge risk exists
  • Budget contingency
  • Monitor for occurrence

Common Construction Risks and Responsesโ€‹

RiskResponse Options
Material escalationLock pricing early, allowances, escalation clause
WeatherSchedule buffer, weather contingency, covered work
Subsurface conditionsGeotechnical study, contingency, differing conditions clause
Permitting delaysEarly submittal, pre-application meetings, float
Design errorsRFI process, constructability review, contingency
Labor shortageEarly recruitment, pre-hire, multiple sources
Subcontractor defaultPrequalification, bonds, backup subs
Owner changesChange order process, document all directions

Risk Monitoringโ€‹

Regular Reviews:โ€‹

  • Weekly (active risks)
  • Monthly (all risks)
  • Major milestones
  • When conditions change

Track:โ€‹

  • Risk status
  • New risks
  • Closed risks
  • Effectiveness of responses

Risk Contingencyโ€‹

Budget Contingency:โ€‹

Risk LevelContingency
Low risk project2-3%
Medium risk5-7%
High risk8-10%+

Schedule Contingency:โ€‹

  • Add float for high-risk activities
  • Buffer before milestones
  • Reasonable overall duration

Risk Communicationโ€‹

Communicate Risks To:โ€‹

  • Project team
  • Management
  • Owner (as appropriate)
  • Subcontractors (their risks)

Risk Escalation:โ€‹

  • Critical risks โ†’ Executive attention
  • Budget impacts โ†’ Finance
  • Schedule impacts โ†’ Operations

  • Bid Pursuit (Go/No-Go)
  • Estimating Standards
  • Change Order Management
  • Claims Procedures

Template provided by support.construction. Proactive risk management protects projects.

Was this page helpful?