Inspection Procedures

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Superintendents, QC Managers, Project Managers


Purpose

Establish procedures for conducting inspections at critical phases of construction to verify quality, compliance with specifications, and readiness for subsequent work.


Inspection Philosophy

"Inspect before covering, not after the call-back."

Principles:

  1. Inspect at each critical phase
  2. Document every inspection
  3. Correct issues before proceeding
  4. Never cover defective work
  5. Involve responsible parties

Types of Inspections

TypeWho ConductsWhen
QC InspectionContractor QCBefore cover-up
Official InspectionBuilding InspectorPer permit
Third-Party TestingTesting AgencyPer spec
Owner/ArchitectDesign TeamProgress and final
SpecialtyCompetent PersonPer OSHA/code

Inspection Timing Matrix

Work PhaseInspection RequiredTriggered By
ExcavationCompetent personBefore entry
FoundationsPre-pour, forms, rebarBefore pour
StructuralConnections, weldsBefore cover
MEP RoughBefore close-upBefore drywall
InsulationBefore coverBefore drywall
WaterproofingBefore coverBefore backfill
FinishesQuality checkBefore punch

Pre-Pour Inspection (Concrete)

When Required:

  • Before any concrete placement
  • Foundations, slabs, walls, elevated decks

Inspection Checklist:

Forms:

  • Correct alignment and dimensions
  • Properly braced and supported
  • Clean (no debris)
  • Release agent applied
  • Snap ties/form ties secure
  • Chamfer strips (if required)

Reinforcement:

  • Correct bar sizes per drawings
  • Correct spacing
  • Adequate cover (chairs, spacers)
  • Lap splices correct length
  • Tied securely
  • Dowels for future work

Embedded Items:

  • Anchor bolts in place
  • Sleeves installed
  • Conduit roughed in
  • Plumbing roughed in
  • Embeds for steel

Ready for Pour:

  • Forms wet down (if required)
  • Mix design approved
  • Pump/conveyance ready
  • Weather acceptable
  • Cure materials on-site

Pre-Close Inspection (MEP Rough-In)

When Required:

  • Before closing walls (drywall, paneling)
  • Before closing ceilings (drop ceiling)

Inspection Checklist:

Mechanical:

  • Ductwork installed per plan
  • Proper support/hangers
  • Seams sealed
  • Dampers accessible
  • Clearances maintained
  • Insulation (if at this stage)

Electrical:

  • Boxes at correct height
  • Proper wire size
  • Supports adequate
  • Code clearances maintained
  • Grounding verified
  • Low voltage roughed

Plumbing:

  • Piping per plan
  • Proper slope (drains)
  • Test caps in place
  • Supports adequate
  • Fire stopping materials ready

Fire Protection:

  • Heads at correct locations
  • Proper coverage
  • Supports adequate
  • Escutcheons ready

General:

  • Blocking installed
  • Penetrations located correctly
  • Fire stopping noted
  • Coordination complete

Structural Steel Inspection

When Required:

  • Connection inspections
  • Weld inspections
  • Before enclosure

Inspection Checklist:

Bolted Connections:

  • Correct bolt size and grade
  • Correct number of bolts
  • Washer placement correct
  • Proper torque verified
  • All holes filled

Welded Connections:

  • Welder certification verified
  • WPS followed
  • Visual inspection complete
  • NDT complete (if required)
  • Weld size per drawings

General:

  • Member sizes correct
  • Orientation correct
  • Elevations correct
  • Plumb and level
  • Touch-up paint applied

Waterproofing/Roofing Inspection

When Required:

  • Before covering/backfill
  • At each layer (multi-ply systems)

Inspection Checklist:

Surface Preparation:

  • Substrate clean and dry
  • Primer applied (if required)
  • Defects repaired
  • Moisture testing (if required)

Membrane Application:

  • Correct material per spec
  • Proper laps and seams
  • Adhesion verified
  • Penetrations sealed
  • Transitions detailed

Flashings:

  • Terminations sealed
  • Corners detailed
  • Penetration flashings
  • Counter-flashing (if required)

Protection:

  • Protection board (below grade)
  • Drainage (if required)
  • Ready for backfill/cover

Final/Punch Inspection

When Required:

  • Before substantial completion
  • Before owner walk

Inspection Checklist:

Overall:

  • All work complete
  • Clean and debris-free
  • Temporary items removed
  • Finishes acceptable

Systems:

  • All systems operational
  • Testing complete
  • Controls functional
  • Balancing complete

Documentation:

  • Inspections passed
  • Test reports complete
  • Certifications obtained
  • As-builts updated

Inspection Documentation

Inspection Report Format:

================================================================
INSPECTION REPORT
================================================================

PROJECT: _________________________ DATE: _______________

INSPECTION TYPE: _________________________________________

LOCATION: ________________________________________________

INSPECTED BY: ____________________________________________

================================================================

ITEMS INSPECTED:

| Item | Spec Ref | Pass | Fail | NA | Comments |
|------|----------|------|------|----|-----------
| | | | | | |
| | | | | | |
| | | | | | |

================================================================

DEFICIENCIES NOTED:

1. ______________________________________________________
Location: ____________________________________________
Action Required: _____________________________________

2. ______________________________________________________
Location: ____________________________________________
Action Required: _____________________________________

================================================================

RESULT:
☐ Approved - Ready to proceed
☐ Approved with conditions (see deficiencies)
☐ Not approved - Correct and reinspect

================================================================

Inspector Signature: _____________________ Date: ________

Acknowledged By: _________________________ Date: ________

================================================================

Third-Party Testing Coordination

Common Tests:

TestWhenWho Schedules
Concrete testingEach pourContractor
Steel inspectionPer planContractor
Soils compactionBefore pavingContractor
HVAC balancingAfter installMechanical sub
Electrical testingAfter installElectrical sub
Roof/wall testingAfter installContractor

Scheduling:

  • 48-hour notice minimum
  • Confirm availability
  • Coordinate with work schedule
  • Have area accessible

Failed Tests:

  • Stop work in affected area
  • Investigate root cause
  • Implement correction
  • Retest
  • Document everything

Building Department Inspections

Common Required Inspections:

InspectionWhen to Call
FoundationForms and rebar ready
UndergroundBefore backfill
Rough frameBefore cover
Rough MEPBefore cover
InsulationBefore cover
DrywallBefore tape/finish
FinalBefore occupancy

Best Practices:

  • Schedule 24-48 hours ahead
  • Have permits posted
  • Have plans on site
  • Be present for inspection
  • Address corrections immediately
  • Get inspection card signed

  • QC Plan Template
  • Pre-Pour Checklist
  • Pre-Close Checklist
  • Inspection Request Form
  • Deficiency Log

Software Integration

BLDR Pro Features:

  • Digital inspection checklists
  • Photo documentation
  • Deficiency tracking
  • Report generation
  • Schedule coordination

Template provided by support.construction. Customize with your company information.