Skip to main content
Skip to main content

Documentation Standards

Document Type: Policy
Version: 1.0
Last Updated: February 2026
Distribute To: All Project Personnel


Purpose

Establish company-wide documentation standards to ensure consistency, protect against disputes, meet compliance requirements, and support project success.


The Golden Rule of Construction Documentation

"If it's not documented, it didn't happen."

In construction disputes, the party with better documentation wins. Every conversation, decision, delay, and issue should be documented.


Daily Documentation Requirements

Daily Reports (Field Personnel)

Due: End of each work day
Who: Superintendent, Foreman, or designated reporter

Required Content:

  • Date, project name, report number
  • Weather conditions (start, end, temperature, precipitation)
  • Manpower by trade (company employees and subs)
  • Work performed (specific locations and activities)
  • Materials received and installed
  • Equipment on site
  • Visitors and inspections
  • Issues, delays, or impacts
  • Safety observations
  • Tomorrow's planned activities
  • Photos (minimum 3-5 per day)

Photo Requirements:

  • Overall site conditions (AM and PM)
  • Work in progress by each active trade
  • Concealed work BEFORE covering
  • Deliveries (especially for tracking purposes)
  • Any issues, defects, or damage
  • Weather conditions if impacting work

Time Documentation

Due: Daily
Who: All employees and supervisors

Required:

  • Start and end times
  • Project/cost code allocation
  • Overtime justification
  • Supervisor approval

For Prevailing Wage/Certified Payroll:

  • Classification and wage rate
  • Fringe benefit allocation
  • Apprentice ratios verified
  • Certified payroll submitted weekly

Project Documentation Requirements

Submittals

Track:

  • Submittal number and revision
  • Date submitted
  • Date required for approval
  • Specification section
  • Current status
  • Reviewer and response date

File Naming: [ProjectNumber]_SUB_[SpecSection]_[Description]_Rev[#]


RFIs (Request for Information)

Track:

  • RFI number
  • Date submitted
  • Response required date
  • Question/request
  • Response received
  • Schedule/cost impact

File Naming: [ProjectNumber]_RFI_[Number]_[Description]

Response Time Standards:

  • Routine RFI: 7 calendar days
  • Urgent RFI: 48 hours
  • Document delays when exceeded

Change Orders

Document:

  • Change order number
  • Description of changed work
  • Reason for change (owner request, field condition, design error, etc.)
  • Cost breakdown (labor, material, equipment, subs, markup)
  • Schedule impact (if any)
  • Approval signatures
  • Date work can proceed

File Naming: [ProjectNumber]_CO_[Number]_[Description]


Meeting Minutes

Document:

  • Date, time, location
  • Attendees (name and company)
  • Agenda items discussed
  • Decisions made
  • Action items (owner, due date)
  • Next meeting date

Distribute: Within 24 hours
File Naming: [ProjectNumber]_MINS_[YYYYMMDD]_[MeetingType]


Photo Documentation Standards

Naming Convention

[ProjectNumber]_[Date]_[Location]_[Description].jpg

Example: 2024-001_20260201_Level2_Electrical-Rough.jpg

Minimum Requirements

Project PhasePhotos/DayFocus Areas
Mobilization10+Existing conditions, lay-down areas
Foundation5-10Excavation, rebar, concrete
Structure5-10Steel, decking, connections
MEP Rough-In10+Before close-up, penetrations
Close-Up5-10Insulation, drywall progress
Finishes5-10Quality, defects, progress
Punch ListAs neededEach deficiency
Closeout20+Final conditions, all areas

What to Always Photograph

  • Existing conditions (before work)
  • Underground work before backfill
  • Concealed work before cover-up
  • Test/inspection results
  • Defects or damaged materials
  • Delays (weather, access issues, etc.)
  • Safety hazards found and corrected
  • Deliveries (quantities, condition)

Filing Structure

Digital File Organization

/Projects
/[ProjectNumber]_[ProjectName]
/01-Contract
/02-Drawings
/03-Specifications
/04-Submittals
/05-RFIs
/06-Change-Orders
/07-Meeting-Minutes
/08-Daily-Reports
/09-Photos
/10-Correspondence
/11-Safety
/12-Financial
/13-Closeout

Retention Requirements

Document TypeRetention Period
ContractsPermanent
As-Built DrawingsPermanent
Insurance certificatesLife of project + 10 years
Financial records7 years
Daily reportsLife of project + 6 years
Safety records5 years or per OSHA
Payroll records7 years (10 for prevailing wage)
General correspondence6 years

Email Documentation

Subject Line Format

[Project Number] - [Topic] - [Action Required/FYI]

Example: PRJ-2024-001 - RFI #45 Response - Action Required

When to Use Email vs. Other Methods

Use Email WhenDon't Use Email When
Paper trail neededSensitive/confidential discussions
Non-urgent mattersComplex negotiations
Distributing documentsEmergency situations
Confirming verbal agreementsMatters requiring nuance
Formal noticesDelivering bad news

Important: Written Confirmation

After any verbal discussion that includes commitments or decisions, send confirmation email:

Subject: Confirmation - [Topic Discussed] - [Date]

[Name],

Per our conversation today, I am confirming the following:
- [Key point 1]
- [Key point 2]
- [Agreed action items]

Please let me know if I have misunderstood anything.

Regards,
[Your name]

Quality Standards

Document Review Checklist

Before submitting any document:

  • Correct project number/name
  • Date is current
  • All required fields completed
  • Spelling and grammar checked
  • Attachments included
  • Correct recipients
  • Appropriate tone

Common Documentation Mistakes to Avoid

❌ Backdating documents
❌ Altering documents after signing
❌ Vague descriptions ("worked on building")
❌ Missing dates or signatures
❌ Photos without context or labels
❌ Informal language in formal documents
❌ Storing documents only locally (no backup)


Tools and Technology

  • Daily Reports: BLDR Pro (mobile-friendly, offline capable)
  • Document Management: Procore, BLDR Pro, or cloud storage
  • Photos: BLDR Pro (auto GPS/timestamp) or dedicated photo app
  • Time Tracking: BLDR Time or BLDR Pro

Backup Requirements

  • All project documents backed up daily
  • Cloud storage preferred
  • Local backup weekly
  • Test restoration quarterly

  • Daily Report Template
  • Photo Log Template
  • RFI Log Template
  • Change Order Form
  • Meeting Minutes Template

Template provided by support.construction. Customize with your company information.