Estimating Standards

Document Type: Standards
Version: 1.0
Last Updated: February 2026
Distribute To: Estimating Department


Purposeโ€‹

Establish consistent standards for preparing accurate, competitive estimates.


Estimating Processโ€‹

Document Review โ†’ Quantity Takeoff โ†’ Pricing โ†’ 
Assembly โ†’ Review โ†’ Final Pricing โ†’ Submit

Estimate Componentsโ€‹

Direct Costs:โ€‹

ComponentDescription
LaborHours ร— hourly rate
MaterialQuantities ร— unit price
EquipmentHours/days ร— rate
SubcontractorsSub quotes

Indirect Costs:โ€‹

ComponentDescription
General ConditionsSite overhead
OverheadCompany overhead
ProfitMargin
ContingencyRisk reserve
BondIf required

Document Reviewโ€‹

Before Takeoff:โ€‹

  • Drawings complete and legible
  • Specifications reviewed
  • Addenda incorporated
  • Questions/clarifications noted
  • Scope clearly defined
  • Bid requirements understood

Note:โ€‹

  • Conflicts between drawings/specs
  • Missing information
  • Ambiguous requirements
  • Special requirements

Quantity Takeoff Standardsโ€‹

General Rules:โ€‹

  1. Measure from contract documents
  2. Use consistent units
  3. Apply appropriate waste factors
  4. Document assumptions
  5. Verify calculations

Takeoff Checklist:โ€‹

  • Scale verified
  • All areas counted
  • Waste factors applied
  • Units consistent
  • Math verified

Common Waste Factors:โ€‹

MaterialWaste %
Concrete5-10%
Rebar5-10%
Lumber10-15%
Drywall5-10%
Roofing5-10%
Paint5-10%
Flooring5-10%

Labor Pricingโ€‹

Labor Rate Components:โ€‹

Base wage
+ Taxes (FICA, FUTA, SUTA)
+ Insurance (WC, GL)
+ Benefits (health, retirement)
+ Training
= Burdened Labor Rate

Productivity Factors:โ€‹

  • Weather conditions
  • Site access
  • Height of work
  • Complexity
  • Crew size
  • Learning curve

Material Pricingโ€‹

Pricing Sources:โ€‹

  • Vendor quotes (preferred)
  • Historical data
  • Published pricing guides
  • Material cost databases

Quote Requirements:โ€‹

  • Current pricing
  • Delivery included
  • Tax status clear
  • Quantity breaks
  • Validity period

Subcontractor Quotesโ€‹

Quote Collection:โ€‹

  • Minimum 3 quotes per trade
  • Complete scope coverage
  • Written quotes only
  • Qualified subs only

Quote Review:โ€‹

  • Scope complete
  • Exclusions acceptable
  • Qualifications noted
  • Insurance adequate
  • Price reasonable

Bid Leveling:โ€‹

  • Compare apples to apples
  • Adjust for scope differences
  • Note qualifications
  • Identify buy-out potential

Markup Guidelinesโ€‹

Standard Markups:โ€‹

Project TypeOverheadProfitTotal
Negotiated10%10%20%
Competitive8%5%13%
Hard Bid6%4%10%
Public5%3%8%

Adjust based on risk, complexity, and market

Contingency:โ€‹

  • Low risk: 2-3%
  • Medium risk: 3-5%
  • High risk: 5-10%

Estimate Summary Formatโ€‹

================================================================
ESTIMATE SUMMARY
================================================================

Project: ________________________ Date: _______________
Estimator: ______________________ Estimate #: __________

================================================================

DIRECT COSTS:
01 General Requirements $________________
02 Existing Conditions $________________
03 Concrete $________________
04 Masonry $________________
05 Metals $________________
06 Wood/Plastics $________________
07 Thermal/Moisture $________________
08 Openings $________________
09 Finishes $________________
10 Specialties $________________
11 Equipment $________________
12 Furnishings $________________
21 Fire Suppression $________________
22 Plumbing $________________
23 HVAC $________________
26 Electrical $________________
โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€
DIRECT COST SUBTOTAL $________________

================================================================

INDIRECT COSTS:
General Conditions $________________
Overhead (__%) $________________
Profit (__%) $________________
Contingency (__%) $________________
Bond (__%) $________________
โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€
INDIRECT COST SUBTOTAL $________________

================================================================

TOTAL ESTIMATE $________________

================================================================

QUALIFICATIONS:
___________________________________________________________
___________________________________________________________

EXCLUSIONS:
___________________________________________________________
___________________________________________________________

================================================================

Quality Checksโ€‹

Before Final Pricing:โ€‹

  • All scope covered
  • Quantities verified
  • Pricing current
  • Calculations checked
  • Subcontractor quotes levelized
  • Markup appropriate
  • Qualifications noted
  • Exclusions clear

Final Review:โ€‹

  • Second estimator review
  • Management review
  • Cost per SF check
  • Historical comparison

Cost Per SF Benchmarksโ€‹

Building TypeLowTypicalHigh
Office (Class A)$200$300$400+
Retail$150$225$350
Warehouse$80$120$180
Industrial$100$150$250
Healthcare$350$500$700+
Education$250$350$500

Varies significantly by location and specifications


  • Bid Pursuit Process
  • Subcontractor Bidding
  • Bid Submission Procedure
  • Cost Code Structure

Template provided by support.construction. Customize with your company information.