Skip to main content
Skip to main content

Work in Progress (WIP) Reporting Procedure

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Accounting, Executives


Purposeโ€‹

Establish procedures for accurate WIP reporting to track project profitability and recognize revenue properly.


What is WIP?โ€‹

Work in Progress (WIP) is a financial report that:

  • Tracks each project's profitability
  • Calculates over/under billings
  • Recognizes revenue properly
  • Required for percentage of completion accounting

WIP Report Componentsโ€‹

For Each Project:โ€‹

FieldDescription
Contract ValueCurrent contract + approved COs
Estimated CostTotal cost to complete project
Cost to DateActual costs incurred
% CompleteCost to date รท Estimated cost
Earned RevenueContract ร— % complete
Billed to DateAmount invoiced
Over/UnderEarned revenue - billed
Projected ProfitContract - estimated cost
Projected MarginProfit รท contract

Percentage Complete Calculationโ€‹

Cost-to-Cost Method (Most Common):โ€‹

                  Costs Incurred to Date
% Complete = โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€โ”€
Total Estimated Costs

Example:โ€‹

  • Estimated total cost: $800,000
  • Costs to date: $400,000
  • % Complete: 50%

Over/Under Billingโ€‹

Over-Billed:โ€‹

  • Billed more than earned
  • Liability on balance sheet
  • Cash received ahead of work
  • Must "earn" this in future

Under-Billed:โ€‹

  • Billed less than earned
  • Asset on balance sheet
  • Work ahead of billing
  • Collect through future billings

Formula:โ€‹

Over/Under = Earned Revenue - Billed to Date

Positive = Under-billed (asset)
Negative = Over-billed (liability)

WIP Report Formatโ€‹

================================================================
WORK IN PROGRESS REPORT
================================================================

Period Ending: ______________________________________________

================================================================

| Project | Contract | Est Cost | Cost TD | % Comp | Earned | Billed | Over/(Under) | Est Profit | Margin |
|---------|----------|----------|---------|--------|--------|--------|--------------|------------|--------|
| PRJ-001 | | | | | | | | | |
| PRJ-002 | | | | | | | | | |
| PRJ-003 | | | | | | | | | |
| TOTAL | | | | | | | | | |

================================================================

SUMMARY:

Total Over-Billed: $____________________
Total Under-Billed: $____________________
Net Over/(Under): $____________________

Total Estimated Profit (Open Jobs): $____________________
Average Margin: ________%

================================================================

Reviewed By: _______________________ Date: _________________

================================================================

WIP Review Processโ€‹

Monthly Steps:โ€‹

Step 1: Update Contract Values

  • Add approved change orders
  • Verify current contract value
  • Include pending (if appropriate)

Step 2: Update Costs to Date

  • All costs posted
  • Accruals for unbilled work
  • Committed costs included

Step 3: Update Estimated Costs

  • Review original estimate
  • Adjust for changes
  • Include costs to complete
  • Update projections

Step 4: Calculate Percentages

  • % complete calculated
  • Revenue recognized
  • Over/under calculated

Step 5: PM Review

  • Each PM reviews their projects
  • Estimates realistic
  • Issues identified

Step 6: Management Review

  • Overall review
  • Problem projects discussed
  • Adjustments approved

Fade Analysisโ€‹

Tracking Profit Changes:โ€‹

MonthEst. ProfitChangeReason
Jan$100,000-Original
Feb$95,000($5,000)Material increase
Mar$90,000($5,000)Extra labor
Apr$85,000($5,000)Change order (pending)

Fade Flags:โ€‹

  • Consecutive profit decreases
  • Significant single-month drops
  • Margin below company average

Estimate to Complete (ETC)โ€‹

Review Regularly:โ€‹

Questions to Ask:

  • What work remains?
  • Are there cost overruns?
  • Pending change orders?
  • Productivity issues?
  • Material price changes?
  • Schedule impacts?

Update ETC When:

  • Monthly (at minimum)
  • After significant events
  • When issues arise
  • Quarterly deep dive

Common WIP Issuesโ€‹

IssueCauseSolution
% complete jumpsDelayed cost postingPost timely
Profit fadesPoor estimate updatesReview estimates monthly
Large under-billingSlow billingBill promptly
Large over-billingFront-loaded SOVReview SOV setup
Negative profitJob problemsEarly intervention

Job Profitability Reviewโ€‹

Green Flags:โ€‹

  • On budget or better
  • Consistent profit estimates
  • Under-billed (slightly)
  • On schedule

Yellow Flags:โ€‹

  • Profit fading
  • Over-billed significantly
  • Behind schedule
  • Change orders pending

Red Flags:โ€‹

  • Negative profit projected
  • Large, unexplained changes
  • Significant fade
  • No recent estimate review

Software Integrationโ€‹

BLDR Pro:

  • Cost tracking
  • % complete calculation
  • Job cost reporting
  • WIP report generation

  • Job Cost Reporting
  • Pay Application Process
  • Change Order Management
  • Monthly Close Process

Template provided by support.construction. Critical for construction financial management.