Labor Productivity Analysis
Document Type: Guide
Version: 1.0
Last Updated: February 2026
Distribute To: CFO, Controller, Operations Manager, Project Managers
Purposeβ
Establish procedures for measuring, analyzing, and improving labor productivity to enhance profitability, improve estimates, and optimize workforce management.
Why Labor Productivity Mattersβ
Construction Labor Reality:β
- Labor typically 30-50% of project cost
- Small productivity changes = big profit impact
- Productivity varies widely (up to 50% between crews)
- Measurement enables improvement
Impact Example:β
10% productivity improvement on $1M labor budget:
= $100,000 savings
= Direct contribution to profit
= Often makes difference between profit and loss
Productivity Metricsβ
Basic Productivity Formula:β
Productivity = Output Γ· Input
Construction examples:
- Linear feet of pipe per hour
- Square feet of drywall per hour
- Cubic yards of concrete per hour
- Units installed per hour
Key Metrics:β
| Metric | Formula | Use |
|---|---|---|
| Labor Factor | Actual Hours Γ· Budget Hours | Overall efficiency |
| Unit Rate | Hours Γ· Units Installed | Specific activity |
| Cost per Unit | Labor $ Γ· Units Installed | Cost tracking |
| Revenue per Hour | Revenue Γ· Labor Hours | Company-wide |
Measuring Productivityβ
Daily Production Report:β
================================================================
DAILY PRODUCTION REPORT
================================================================
Project: _______________________ Date: _______________
Foreman/Super: _______________________
================================================================
LABOR:
| Employee | Classification | Hours | Cost Code |
|----------|----------------|-------|-----------|
| | | | |
| | | | |
| | | | |
Total crew size: _____
Total hours: _____
----------------------------------------------------------------
PRODUCTION:
| Activity | Cost Code | Units | Unit Type | Hours |
|----------|-----------|-------|-----------|-------|
| | | | | |
| | | | | |
Productivity: _____ units/hour
Budget productivity: _____ units/hour
Performance: _____% of budget
----------------------------------------------------------------
CONDITIONS:
Weather: β Normal β Hot β Cold β Rain β Wind
Site access: β Good β Limited β Poor
Material availability: β Good β Some delays β Waiting
Equipment availability: β Good β Issues: _________________
Coordination with others: β Good β Conflicts
----------------------------------------------------------------
ISSUES/DELAYS:
| Issue | Hours Lost | Impact |
|-------|------------|--------|
| | | |
----------------------------------------------------------------
TOMORROW'S PLAN:
Activity: _______________________
Target production: _______________________
Resources needed: _______________________
================================================================
Weekly Productivity Summary:β
================================================================
WEEKLY PRODUCTIVITY SUMMARY
================================================================
Project: _______________________ Week Ending: _______________
================================================================
LABOR SUMMARY:
| Cost Code | Description | Budget | Actual | Variance | % |
|-----------|-------------|--------|--------|----------|---|
| | | | | | |
| | | | | | |
| TOTAL | | | | | |
Overall labor factor: _____
over 1.0 = Using more hours than budget (inefficient)
under 1.0 = Using fewer hours than budget (efficient)
----------------------------------------------------------------
PRODUCTION BY ACTIVITY:
| Activity | Units | Hours | Unit/Hr | Budget | % Budget |
|----------|-------|-------|---------|--------|----------|
| | | | | | |
----------------------------------------------------------------
PRODUCTIVITY TREND:
| Week | Labor Factor | Best Day | Worst Day |
|------|--------------|----------|-----------|
| -4 | | | |
| -3 | | | |
| -2 | | | |
| -1 | | | |
| This | | | |
Trend: β Improving β Stable β Declining
================================================================
Productivity Analysisβ
Labor Factor Analysis:β
================================================================
LABOR FACTOR ANALYSIS
================================================================
Project: _______________________ Through: _______________
================================================================
BY COST CODE:
| Cost Code | Description | Budget Hrs | Actual Hrs | Factor |
|-----------|-------------|------------|------------|--------|
| | | | | |
| | | | | |
| PROJECT | | | | |
----------------------------------------------------------------
BEST PERFORMING (Factor < 0.95):
| Cost Code | Factor | Reason for Good Performance |
|-----------|--------|----------------------------|
| | | |
----------------------------------------------------------------
WORST PERFORMING (Factor > 1.05):
| Cost Code | Factor | Reason | Corrective Action |
|-----------|--------|--------|-------------------|
| | | | |
----------------------------------------------------------------
ROOT CAUSE ANALYSIS:
High labor factors typically caused by:
β Estimating error (budget too low)
β Scope creep (more work than estimated)
β Rework/quality issues
β Material/equipment delays
β Crew inexperience
β Supervision gaps
β Site conditions
β Weather impacts
β Coordination issues
β Other: _______________________________
Action plan:
___________________________________________________________
================================================================
Productivity by Crew:β
================================================================
CREW PRODUCTIVITY COMPARISON
================================================================
Project: _______________________ Activity: _______________
================================================================
| Crew/Foreman | Hours | Units | Productivity | % of Best |
|--------------|-------|-------|--------------|-----------|
| Crew A | | | | |
| Crew B | | | | |
| Crew C | | | | |
| AVERAGE | | | | |
Best crew: _______________________
Gap from best to worst: _____%
----------------------------------------------------------------
ANALYSIS:
What makes the best crew more productive?
β Experience level
β Crew composition
β Leadership/supervision
β Planning/organization
β Tool/equipment management
β Work habits
β Other: _______________________________
Improvement opportunity if all crews matched best:
Hours saved: _____
Dollar savings: $_________________
================================================================
Productivity Factorsβ
Factors Affecting Productivity:β
| Factor | Impact Range | Controllable? |
|---|---|---|
| Crew experience | Β±30% | Partially |
| Supervision quality | Β±25% | Yes |
| Planning/scheduling | Β±20% | Yes |
| Material availability | Β±20% | Yes |
| Tool/equipment | Β±15% | Yes |
| Weather | Β±15% | No |
| Site conditions | Β±15% | Partially |
| Overtime fatigue | -10-25% | Yes |
| Learning curve | -20% initial | Expected |
| Rework | -5-15% | Yes |
Adjustment Factors:β
================================================================
PRODUCTIVITY ADJUSTMENT FACTORS
================================================================
Standard productivity rate: _____ units/hour
ADJUSTMENT FOR CONDITIONS:
| Condition | Factor | Adjusted Rate |
|-----------|--------|---------------|
| Overtime (over 40 hrs/wk) | 0.90 | |
| Overtime (over 50 hrs/wk) | 0.80 | |
| Hot weather (over 95Β°F) | 0.85 | |
| Cold weather (under 32Β°F) | 0.85 | |
| Confined space | 0.75 | |
| Heights (over 30 ft) | 0.85 | |
| Occupied building | 0.85 | |
| Remote location | 0.90 | |
| Night shift | 0.90 | |
| New crew/learning | 0.75 | |
Applied adjustment: _____
Adjusted productivity: _____ units/hour
================================================================
Improving Productivityβ
Productivity Improvement Plan:β
================================================================
PRODUCTIVITY IMPROVEMENT PLAN
================================================================
Project: _______________________ Prepared: _______________
Current overall labor factor: _____
Target labor factor: _____
Improvement needed: _____%
----------------------------------------------------------------
IMPROVEMENT INITIATIVES:
1. PLANNING & SCHEDULING:
β Detailed daily work plans
β Look-ahead scheduling
β Pre-task briefings
Expected impact: _____% improvement
2. MATERIAL MANAGEMENT:
β Material staged before work
β Just-in-time delivery
β Kitting/pre-assembly
Expected impact: _____% improvement
3. TOOL & EQUIPMENT:
β Right tools available
β Equipment maintained
β Specialized tools where needed
Expected impact: _____% improvement
4. CREW OPTIMIZATION:
β Right crew size
β Skill matching to work
β Consistent crew assignments
Expected impact: _____% improvement
5. SUPERVISION:
β Adequate span of control
β Clear expectations
β Regular feedback
Expected impact: _____% improvement
----------------------------------------------------------------
IMPLEMENTATION:
| Initiative | Owner | Start Date | Target Improvement |
|------------|-------|------------|-------------------|
| | | | |
Measurement: Weekly labor factor tracking
Review: Weekly PM review
================================================================
Quick Productivity Wins:β
| Action | Typical Impact | Implementation |
|---|---|---|
| Start on time | 3-5% | Enforce start times |
| Reduce travel time | 2-4% | Stage materials nearby |
| Pre-task planning | 5-10% | Morning briefings |
| Tool organization | 2-3% | Job boxes, shadow boards |
| Material staging | 5-8% | Night/early delivery |
| Reduce rework | 5-10% | Quality checks |
| Minimize overtime | 5-15% | Better planning |
Estimating Feedbackβ
Productivity Database Update:β
================================================================
PRODUCTIVITY DATA UPDATE
================================================================
Activity: _______________________
Project: _______________________
================================================================
HISTORICAL DATA:
| Project | Year | Units | Hours | Productivity | Conditions |
|---------|------|-------|-------|--------------|------------|
| | | | | | |
| | | | | | |
| | | | | | |
Historical average: _____ units/hour
Standard deviation: _____
----------------------------------------------------------------
THIS PROJECT:
Units: _____
Hours: _____
Productivity: _____ units/hour
Conditions: _______________________
Variance from average: _____%
----------------------------------------------------------------
DATABASE UPDATE:
β Update estimating database
β Update crew planning
β Document lessons learned
New recommended rate: _____ units/hour
Approved by: _______________________
================================================================
Reportingβ
Monthly Productivity Report:β
================================================================
MONTHLY PRODUCTIVITY REPORT
================================================================
Month: _______________
================================================================
COMPANY SUMMARY:
Revenue: $_________________
Total labor hours: _____
Revenue per labor hour: $_____
Target: $_____
Variance: $_____
----------------------------------------------------------------
BY PROJECT:
| Project | Labor Factor | This Month | YTD | Trend |
|---------|--------------|------------|-----|-------|
| | | | | βββ |
| | | | | βββ |
| AVERAGE | | | | |
----------------------------------------------------------------
TOP PERFORMERS:
| Project | Labor Factor | Key Success Factors |
|---------|--------------|---------------------|
| | | |
----------------------------------------------------------------
NEEDS IMPROVEMENT:
| Project | Labor Factor | Issues | Action Plan |
|---------|--------------|--------|-------------|
| | | | |
----------------------------------------------------------------
PRODUCTIVITY INITIATIVES:
| Initiative | Status | Measured Impact |
|------------|--------|-----------------|
| | | |
================================================================
Software Integrationβ
BLDR Time Integration:β
- Real-time labor hour capture
- GPS verification of on-site time
- Cost code allocation
- Automatic productivity calculation
- Dashboard visibility
Benefits:β
- Accurate data
- Less administrative burden
- Real-time visibility
- Trend analysis
- Crew comparisons
Related Documentsβ
- Job Costing Procedures
- Time Tracking Procedures
- Estimating Standards
- Cost Control Procedures
Template provided by support.construction. Productivity is the hidden profit driverβmeasure it, manage it, improve it.