Skip to main content
Skip to main content

Schedule of Values (SOV) Setup

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: AR Team, Project Managers, Estimating


Purpose

Establish a consistent process for creating the Schedule of Values (SOV) to ensure accurate billing, proper cost tracking, and contract compliance.


What is a Schedule of Values?

The Schedule of Values (SOV) is a detailed breakdown of the contract price into component parts that will be used for:

  • Monthly progress billing (AIA G703)
  • Cost tracking and management
  • Payment verification by owner/architect
  • Contract administration

When to Create the SOV

Timeline:

  • After contract execution
  • Before first pay application
  • Typically within 10-14 days of contract
  • Must be approved before billing can begin

SOV Development Process

Step 1: Gather Information

Required Documents:

  • Executed contract
  • Final estimate/budget
  • Specification sections
  • Subcontract awards
  • Owner SOV requirements (if specified)

Review Contract Requirements:

  • Number of line items required
  • Format requirements
  • Level of detail required
  • Approval process
  • Modification procedures

Step 2: Determine SOV Structure

Organization Options:

By CSI Division:

Division 03 - Concrete
Division 04 - Masonry
Division 05 - Metals
Division 06 - Wood & Plastics
...

By Project Phase:

Phase 1 - Sitework
Phase 2 - Foundation
Phase 3 - Structure
Phase 4 - Building Envelope
Phase 5 - MEP
Phase 6 - Finishes

By Building/Area:

Building A
Building B
Site Improvements

Best Practice: Match owner's requirements, or use CSI divisions if no preference


Step 3: Create Line Items

Line Item Guidelines:

DO:

  • Create enough detail for clear progress tracking
  • Align with contract scope divisions
  • Match subcontract breakdowns
  • Enable meaningful monthly billing
  • Include all work in original scope

DON'T:

  • Create too few line items (hard to show progress)
  • Create too many line items (administrative burden)
  • Front-load values (appears as overbilling)
  • Leave out scope items

Typical Number of Line Items:

  • Small project ($500K-$2M): 20-40 items
  • Medium project ($2M-$10M): 40-80 items
  • Large project ($10M+): 80-150+ items

Step 4: Assign Values

Value Assignment Methods:

1. From Estimate:

  • Use estimate breakdown
  • Adjust for contract changes
  • Ensure total matches contract

2. From Subcontracts:

  • Use subcontractor SOVs
  • Add GC markup/overhead
  • Verify sub SOV totals match contracts

3. From Historical Data:

  • Use similar project percentages
  • Adjust for project specifics

Balancing Requirements:

  • Individual line items must be reasonable
  • Total must equal contract sum exactly
  • Avoid obvious front-loading
  • Support with backup if questioned

Step 5: Include Required Items

Standard Line Items:

ItemDescriptionNotes
General ConditionsSite overhead, supervisionOften 5-10%
MobilizationSite setup, temp facilitiesOften front-loaded
Bonds & InsuranceProject-specific costsFixed amount
PermitsBuilding permit, other feesAs incurred
Fee/Overhead/ProfitGC marginMay be last item

Trade Line Items (Example):

  • Sitework (excavation, utilities, paving)
  • Concrete (foundations, slabs, structure)
  • Masonry
  • Structural Steel
  • Carpentry (rough, finish)
  • Roofing
  • Doors/Frames/Hardware
  • Glass & Glazing
  • Drywall/Ceilings
  • Flooring
  • Painting
  • Specialties
  • Plumbing
  • HVAC
  • Electrical
  • Fire Protection

Step 6: Internal Review

Before Submission, Review:

  • All scope included
  • Total matches contract sum
  • Values are reasonable (not front-loaded)
  • Matches estimate/budget breakdown
  • Subcontractor SOVs incorporated
  • General conditions appropriate
  • Owner requirements met
  • Format is correct

Step 7: Submit for Approval

Submission:

  • Submit to owner/architect per contract
  • Include cover letter if required
  • Allow time for review and revision

Typical Review Items (Owner/Architect):

  • Reasonableness of values
  • Adequate detail
  • No apparent front-loading
  • Alignment with contract

If Revisions Required:

  • Discuss concerns
  • Provide backup/justification
  • Revise as agreed
  • Resubmit promptly

Step 8: Finalize and Distribute

Upon Approval:

  1. Document approval date
  2. Distribute to project team
  3. Enter in billing system
  4. Provide to subcontractors (their portions)
  5. Set up cost tracking alignment

SOV Template

================================================================
SCHEDULE OF VALUES
================================================================

PROJECT: ________________________ CONTRACT #: ____________

OWNER: __________________________ DATE: ____________

CONTRACTOR: _____________________

ORIGINAL CONTRACT SUM: $_______________

================================================================

| Item | Description | Specification | Scheduled |
| No. | | Section | Value |
|------|--------------------|---------------|-----------|
| 1 | General Conditions | 01000 | $ |
| 2 | Mobilization | 01500 | $ |
| 3 | Bonds & Insurance | 01400 | $ |
| 4 | Sitework | 02000 | $ |
| 5 | Concrete | 03000 | $ |
| 6 | Masonry | 04000 | $ |
| 7 | Structural Steel | 05100 | $ |
| 8 | Misc. Metals | 05500 | $ |
| 9 | Rough Carpentry | 06100 | $ |
| 10 | Finish Carpentry | 06200 | $ |
| 11 | Thermal/Moisture | 07000 | $ |
| 12 | Roofing | 07500 | $ |
| 13 | Doors & Frames | 08100 | $ |
| 14 | Hardware | 08700 | $ |
| 15 | Glass & Glazing | 08800 | $ |
| 16 | Drywall | 09250 | $ |
| 17 | Acoustical Ceiling | 09510 | $ |
| 18 | Flooring | 09600 | $ |
| 19 | Painting | 09900 | $ |
| 20 | Specialties | 10000 | $ |
| 21 | Equipment | 11000 | $ |
| 22 | Furnishings | 12000 | $ |
| 23 | Plumbing | 15400 | $ |
| 24 | HVAC | 15700 | $ |
| 25 | Electrical | 16000 | $ |
| 26 | Fire Protection | 15300 | $ |
|------|--------------------|---------------|-----------|
| | TOTAL | | $ |
================================================================

Submitted By: _________________________ Date: ____________

Approved By: __________________________ Date: ____________

================================================================

Front-Loading Considerations

What is Front-Loading?

Assigning higher values to early work items to receive more payment in early project stages.

Why It's Problematic:

  • Creates overbilled position
  • May require credit if project stops
  • Erodes trust with owner
  • May violate contract terms

How to Avoid:

  • Base values on actual costs
  • Keep mobilization reasonable (3-5%)
  • Don't inflate early trade work
  • Be prepared to justify any questioned values

Acceptable Early Items:

  • Actual mobilization costs
  • Permit fees
  • Bonds/insurance (one-time)
  • Early procurement (long-lead)

Modifying the SOV

When Modifications Occur:

  • Change orders approved
  • Scope additions/deletions
  • Reallocation between items

Process:

  1. Add new line items for change orders
  2. Adjust values as needed
  3. Submit revised SOV to owner
  4. Obtain approval
  5. Use revised SOV for future billing

Change Order Line Items:

  • Add as separate line items
  • Number as CO-001, CO-002, etc.
  • Include description and approved amount

Aligning SOV with Cost Tracking

Best Practice:

SOV line items should align with:

  • Budget/estimate
  • Job cost codes
  • Subcontract values

Benefits:

  • Easy billing preparation
  • Accurate cost-to-complete
  • Simple variance analysis
  • Better project control

  • Pay Application Process
  • Change Order Management
  • Project Startup Procedure
  • Cost Management Procedure

Software Integration

BLDR Pro Features:

  • SOV creation and management
  • Alignment with cost codes
  • Automatic G703 generation
  • Change order integration
  • Progress tracking

Template provided by support.construction. Customize with your company information.