💰 Change Order Request Generator
Get your change orders approved — with proper documentation and pricing.
Change Order Request Template
CHANGE ORDER REQUEST
Project: [Project Name]
COR Number: [COR-XXX]
Date: [Date]
To: [Owner/GC Name and Contact]
From: [Your Company]
Contract: [Contract Number/Date]
1. Description of Change
Summary
[One paragraph describing the change]
Reason for Change
- Owner-requested change
- Design error/omission
- Field condition (unforeseen)
- Code/regulatory requirement
- Value engineering
- Other: ___________
Reference Documents
- RFI: [Number, if applicable]
- ASI: [Number, if applicable]
- Drawing revision: [Number]
- Directive: [Reference]
2. Scope of Work
Work Included
- [Detailed item 1]
- [Detailed item 2]
- [Detailed item 3]
Work Excluded
- [Item explicitly not included]
- [Item explicitly not included]
Assumptions
- [Key assumption 1]
- [Key assumption 2]
3. Cost Breakdown
Labor
| Trade | Hours | Rate | Extension |
|---|---|---|---|
| [Trade 1] | $ | $ | |
| [Trade 2] | $ | $ | |
| Subtotal: | $ |
Materials
| Description | Quantity | Unit | Unit Price | Extension |
|---|---|---|---|---|
| $ | $ | |||
| $ | $ | |||
| Subtotal: | $ |
Equipment
| Description | Duration | Rate | Extension |
|---|---|---|---|
| $ | $ | ||
| Subtotal: | $ |
Subcontractors
| Subcontractor | Scope | Amount |
|---|---|---|
| $ | ||
| $ | ||
| Subtotal: | $ |
Summary
| Category | Amount |
|---|---|
| Labor | $ |
| Materials | $ |
| Equipment | $ |
| Subcontractors | $ |
| Direct Cost | $ |
| Overhead (___%) | $ |
| Profit (___%) | $ |
| TOTAL | $ |
4. Schedule Impact
Time Requested
- No time extension required
- _____ calendar days extension requested
- _____ working days extension requested
Justification for Time
[Explain why additional time is needed]
Critical Path Impact
- Work is on critical path
- Work affects critical path activity: [Activity name]
- Work is not on critical path
5. Supporting Documentation
Attached
- Marked-up drawings
- Product data/specifications
- Subcontractor quotes
- Material quotes/invoices
- Labor time sheets
- Equipment rental receipts
- Photos
- Correspondence (RFI, email, directive)
6. Signatures
Submitted by:
_________________________ Date: _________ [Name, Title] [Company]
For Owner/GC Use:
- Approved as submitted
- Approved with modifications: ___________
- Rejected. Reason: ___________
- Returned for additional information: ___________
_________________________ Date: _________ [Authorized Signature]
Sample Change Order Requests
Sample: Owner-Requested Addition
Description: Add (4) additional electrical outlets in Conference Room 201 per Owner's verbal direction on [date], confirmed via email dated [date].
Scope:
- Furnish and install (4) 20A duplex receptacles
- Run conduit and wire from Panel 2A
- Patch drywall at outlet locations
- Paint patches to match existing
Cost: $2,850
- Labor: 16 hours × $85 = $1,360
- Materials: $490
- Subtotal: $1,850
- O&P (15%): $277.50
- Contingency (5%): $92.50
- Drywall/paint allowance: $630
Time: No extension (can perform during normal sequence)
Sample: Unforeseen Condition
Description: Additional foundation work required due to unsuitable soil conditions discovered during excavation at Grid Lines A-B/1-3. Geotechnical report indicated suitable bearing at 4' depth; actual suitable bearing encountered at 7' depth.
Reference: Geotechnical Report dated [date], Field Condition Report dated [date]
Scope:
- Additional excavation: 3' depth × 1,200 SF = 133 CY
- Imported structural fill: 133 CY
- Compaction testing (additional)
- Re-survey for adjusted elevations
Cost: $18,500 [Detailed breakdown attached]
Time: 5 working days (critical path)
Sample: Design Error/Omission
Description: Structural drawings S-201 and S-202 do not show beam-to-column connection details for moment frames at Grid Lines C and D. Connection details are required for fabrication.
Reference: RFI-042 dated [date], response received [date]
Scope:
- Fabricate moment connections per RFI response
- Additional field welding (CJP welds not in original scope)
- Additional inspection (MT/UT testing)
Cost: $24,200 [Detailed breakdown attached]
Time: 8 working days (awaiting detail caused delay; fabrication lead time extended)
Tips for Approval
- Submit quickly — Don't wait until end of project
- Reference the directive — RFI, ASI, email, verbal (confirmed)
- Be specific — Vague CORs get rejected or negotiated down
- Include backup — Quotes, time sheets, receipts
- Fair pricing — Excessive markup invites scrutiny
- Claim time — If it affects schedule, ask for days