📋 RFI Generator
Create RFIs that get answered quickly and protect your schedule.
What Makes a Good RFI?
A well-written RFI:
- Has a clear, specific question
- References exact drawings/specs
- Proposes a solution
- States the schedule impact
- Is easy to answer quickly
RFI Structure
1. Subject Line
Be specific and searchable:
- ❌ "Question about plumbing"
- ✅ "Conflict: 4" waste line at Grid B-3 per P-201"
2. Drawing/Spec Reference
Always include:
- Drawing number (P-201, A-301)
- Detail number (Detail 3)
- Spec section (Division 22 - Plumbing)
- Grid lines/room numbers
3. The Question
One issue per RFI. Be specific:
- What exactly is unclear?
- What conflict exists?
- What information is missing?
4. Suggested Solution
Make it easy to say "yes":
- Option A: [Proposed solution]
- Option B: [Alternative]
- Recommend: Option A because [reason]
5. Impact Statement
Create urgency:
- "Work scheduled to begin [date]"
- "Response needed by [date] to avoid delay"
- "X days delay anticipated if not resolved"
RFI Template
Copy and customize this template:
RFI Number: [Auto-generated or manual]
Date: [Today's date]
Project: [Project name and number]
To: [Architect/Engineer name]
From: [Your company, contact name]
Subject: [Specific, searchable subject]
Drawing/Spec Reference:
- Drawing: [Number and title]
- Detail: [Detail number if applicable]
- Specification: [Section number]
- Location: [Grid lines, room, floor]
Question: [Clear, specific question — one issue only]
Background: [Brief context if needed — what led to this question]
Suggested Solution:
- Option A: [Description]
- Option B: [Description]
- Other: [Please advise]
Recommendation: Option [A/B] because [brief reason]
Schedule Impact:
- Work in this area scheduled: [Date]
- Response needed by: [Date]
- Potential delay if not resolved: [X days]
Attachments:
- Marked-up drawing
- Site photo
- Product data
- Other: ___________
Sample RFIs
Conflict RFI
Subject: Conflict: HVAC duct and structural beam at Grid C-5
Drawing Reference:
- Mechanical: M-201, Detail 4
- Structural: S-102
- Location: Grid C-5, 2nd floor
Question: The 24"×12" supply duct shown routing east-west at elevation 12'-6" conflicts with the W12×26 beam shown at the same elevation. Please confirm preferred resolution.
Suggested Solution:
- Option A: Lower duct to 11'-6" (verify ceiling height acceptable)
- Option B: Route duct south of beam (adds 8 LF)
- Option C: Provide beam penetration detail
Recommendation: Option A maintains shortest route. Ceiling height would be 9'-6" in corridor, which appears acceptable per A-201.
Schedule Impact:
- Duct installation scheduled: Next Monday
- Response needed by: Thursday
- Delay if unresolved: 3-5 days while crew moves to other areas
Missing Information RFI
Subject: Missing: Fire rating for door D-215
Drawing Reference:
- Door schedule: A-801
- Door location: A-102
- Specification: Section 08 11 00
Question: Door D-215 is not listed in the door schedule. Please confirm door type, fire rating, and hardware group.
Suggested Solution: Based on adjacent doors in this fire-rated corridor, we assume:
- 90-minute fire-rated hollow metal frame and door
- Hardware Group 3 per spec
- Please confirm or advise
Schedule Impact:
- Door frame rough-in: This week
- Door lead time: 4 weeks
- Response needed by: Tomorrow to maintain door delivery schedule
Clarification RFI
Subject: Clarification: Finish floor elevation at building transition
Drawing Reference:
- Architectural: A-201, A-202
- Structural: S-101
- Location: Grid line A, between Buildings 1 and 2
Question: A-201 shows FFE at Building 1 connection as 100'-0". A-202 shows FFE at Building 2 connection as 100'-3". Please confirm intended elevation at the transition and whether a ramp or step is required.
Suggested Solution:
- Option A: Ramp at 1:12 slope over 3'-0"
- Option B: Single step with nosing
- Option C: Adjust one building's FFE
Schedule Impact:
- Concrete scheduled: Next week
- Response needed by: Friday
- Surveyor needs 2 days notice for layout
Tips for Faster Responses
- One issue per RFI — Multi-part RFIs get stuck
- Attach marked drawings — Highlight the issue
- Propose solutions — Make "approved" easy
- State deadline clearly — "Need by [date]"
- Follow up — Call if no response in 3 days