Backcharge Procedure

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Superintendents, AP


Purpose

Establish a fair, documented process for charging subcontractors for work performed on their behalf or to correct deficiencies.


What is a Backcharge?

A backcharge is a deduction from a subcontractor's payment for:

  • Work GC performed that was sub's responsibility
  • Damage caused by sub
  • Costs incurred due to sub's failure to perform
  • Cleanup performed by GC
  • Shared costs allocated to sub

When to Backcharge

Legitimate Reasons:

  • Sub-caused damage to other work
  • Failure to complete punch list
  • Failure to clean work area
  • Use of GC equipment/materials
  • Delays caused by sub
  • Coordination failures
  • Safety violations requiring correction
  • Defective work correction

NOT Appropriate:

  • Disputed scope items
  • Unsubstantiated claims
  • Retaliation for complaints
  • Estimated costs without documentation

Backcharge Process

Step 1: Document the Issue

Before Any Work:

  • Identify the problem
  • Photograph conditions
  • Note contract requirement
  • Notify subcontractor in writing

Step 2: Notify Subcontractor

Written Notice Must Include:

  • Description of deficiency
  • Contract reference
  • Deadline to correct
  • Consequences if not corrected

Allow Reasonable Time:

  • Emergency: Immediate
  • Urgent: 24-48 hours
  • Standard: 3-5 days

Step 3: Perform Work (If Sub Doesn't)

If Sub Fails to Respond:

  • Document notification attempts
  • Perform necessary work
  • Track all costs carefully
  • Continue documentation

Step 4: Calculate Costs

Include:

  • Labor (actual hours × rate)
  • Materials (with receipts)
  • Equipment (rental rates)
  • Supervision/overhead

Apply Markup:

  • Per subcontract terms
  • Typically 10-15% overhead

Step 5: Issue Backcharge

Formal Backcharge Notice:

  • Reference original notice
  • Detail work performed
  • Itemize all costs
  • Attach supporting documentation
  • State amount to be deducted

Step 6: Process Deduction

Deduct From:

  • Next progress payment
  • Retention
  • Final payment

Backcharge Notice Form

================================================================
BACKCHARGE NOTICE
================================================================

Backcharge #: ____________ Date: ____________

TO: ________________________________________________________
(Subcontractor)

PROJECT: ___________________________________________________

SUBCONTRACT #: _____________________________________________

================================================================

DESCRIPTION OF BACKCHARGE:

Original Issue:
___________________________________________________________
___________________________________________________________

Date Notified: ______________________________________________

Contract Reference: _________________________________________

Subcontractor Response: ☐ None ☐ Inadequate ☐ Refused

================================================================

WORK PERFORMED BY GC:

Date(s): ___________________________________________________

Description:
___________________________________________________________
___________________________________________________________

================================================================

COST BREAKDOWN:

Labor:
| Description | Hours | Rate | Total |
|-------------|-------|------|-------|
| | | | |
| | | | |
Labor Subtotal: $________________

Materials:
| Item | Quantity | Cost | Total |
|------|----------|------|-------|
| | | | |
| | | | |
Materials Subtotal: $________________

Equipment:
| Item | Hours/Days | Rate | Total |
|------|------------|------|-------|
| | | | |
Equipment Subtotal: $________________

SUBTOTAL: $________________
Overhead/Markup (___%): $________________
TOTAL BACKCHARGE: $________________

================================================================

SUPPORTING DOCUMENTATION ATTACHED:
☐ Original notice to subcontractor
☐ Photos
☐ Time records
☐ Material receipts
☐ Equipment records
☐ Other: _________________

================================================================

This amount will be deducted from your next payment unless
disputed in writing within 10 days.

Project Manager: ____________________ Date: ________________

================================================================

SUBCONTRACTOR ACKNOWLEDGMENT:

☐ Accepted ☐ Disputed (see attached response)

Signature: _________________________ Date: ________________

================================================================

Documentation Requirements

Required for Valid Backcharge:

  • Written notice to sub (with date)
  • Contract reference
  • Reasonable time to cure
  • Proof of non-performance
  • Cost documentation
  • Photos (before/after)
  • Time records (if labor)
  • Receipts (if materials)

Common Backcharge Categories

CategoryDocumentation Needed
CleanupPhotos, labor records
Damage repairPhotos, repair costs
Punch listList, notice, completion costs
Schedule delayImpact analysis, costs
Safety correctionCitation, correction costs

Dispute Resolution

If Sub Disputes:

  1. Meet to discuss
  2. Review documentation
  3. Negotiate if appropriate
  4. Document resolution
  5. Escalate if necessary

Contract Provisions:

  • Follow dispute resolution clause
  • Maintain records
  • Seek legal counsel if significant

  • Subcontract Agreement
  • Change Order Procedure
  • Punch List Procedure
  • Coordination Procedure

Template provided by support.construction. Customize with your company information.