Site Logistics Planning

Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Superintendents, Project Managers


Purposeโ€‹

Establish procedures for planning and managing site logistics to support efficient construction operations.


Site Logistics Componentsโ€‹

Key Elements:โ€‹

  • Site access and circulation
  • Material staging and storage
  • Equipment placement
  • Temporary facilities
  • Safety and security
  • Utilities
  • Environmental controls

Site Logistics Planโ€‹

When to Develop:โ€‹

  • During preconstruction
  • Update at major phases
  • Review monthly

Plan Contents:โ€‹

  1. Site Plan Drawing

    • Property boundaries
    • Building footprint
    • Access points
    • Staging areas
    • Storage locations
    • Equipment positions
    • Temporary facilities
    • Pedestrian routes
    • Vehicle routes
  2. Written Procedures

    • Delivery scheduling
    • Material handling
    • Security protocols
    • Emergency access

Site Accessโ€‹

Vehicle Access:โ€‹

ElementConsiderations
Entry pointsLocation, capacity, hours
Traffic flowOne-way, two-way, turns
Road conditionStabilized, paved, gravel
Weight limitsBridge capacity, soil conditions
Height restrictionsOverhead lines, structures
Public interfaceFlag persons, signage

Pedestrian Access:โ€‹

  • Separate from vehicles when possible
  • Defined walkways
  • Signage
  • Safety barriers

Delivery Scheduling:โ€‹

  • Schedule major deliveries
  • Stagger to prevent congestion
  • Coordinate with work activities
  • Communicate requirements

Material Stagingโ€‹

Staging Area Planning:โ€‹

Considerations:

  • Size needed per phase
  • Proximity to installation
  • Protection from weather
  • Security requirements
  • Ground conditions
  • Access for unloading

Material Types:โ€‹

MaterialStaging Needs
Steel/structuralCrane access, blocking
Mechanical equipmentProtection, rigging access
FinishesInterior, climate control
ElectricalSecure, organized
DrywallFlat, dry, close to install
Concrete formsOrganized, near use

Just-In-Time Delivery:โ€‹

  • Minimize on-site storage
  • Coordinate with schedule
  • Reduce handling
  • Protect materials

Equipment Placementโ€‹

Planning Considerations:โ€‹

EquipmentPlacement Factors
Tower craneCoverage, foundations, swing
Mobile craneAccess, setup, ground conditions
HoistLocation, capacity, timing
Concrete pumpReach, access, cleanup
GeneratorsNoise, exhaust, fuel access

Equipment Schedule:โ€‹

  • When needed
  • How long on site
  • Access requirements
  • Removal timing

Temporary Facilitiesโ€‹

Field Office:โ€‹

RequirementTypical
SizeBased on team size
LocationVisible, accessible
UtilitiesPower, data, water
FeaturesMeeting space, plan room

Worker Facilities:โ€‹

  • Break areas
  • Restrooms (OSHA requirements)
  • Drinking water
  • Warming/cooling areas
  • First aid station

Storage:โ€‹

  • Tool storage (secure)
  • Material storage
  • Flammable storage
  • Waste containers

Temporary Utilitiesโ€‹

Power:โ€‹

NeedSolution
Construction powerTemp service, generator
Office powerSame or separate
Tool powerDistribution, GFCIs

Water:โ€‹

  • Source (temp connection, tank)
  • Distribution
  • Testing/flushing needs

Sanitary:โ€‹

  • Portable toilets (1:20 workers minimum)
  • Handwash stations
  • ADA accessible units

Safety Considerationsโ€‹

Site Safety:โ€‹

  • Perimeter fencing
  • Controlled access
  • Signage
  • Emergency routes
  • Fire access lanes

Traffic Safety:โ€‹

  • Speed limits
  • Pedestrian separation
  • Backing safety
  • Spotter requirements

Securityโ€‹

Security Measures:โ€‹

MeasureWhen
FencingAlways (minimum)
Locked gatesAfter hours
Security guardsHigh-risk sites/phases
CamerasValuable materials, high risk
LightingPerimeter, entries

Theft Prevention:โ€‹

  • Secure storage
  • Inventory tracking
  • Delivery verification
  • Tool tracking
  • Lighting

Environmental Controlsโ€‹

Stormwater (SWPPP):โ€‹

  • Erosion controls
  • Sediment controls
  • Tracking controls
  • Materials storage

Dust Control:โ€‹

  • Water trucks
  • Stabilization
  • Covered loads

Noise/Hours:โ€‹

  • Local restrictions
  • Neighbor communication
  • Schedule accordingly

Site Logistics Plan Templateโ€‹

================================================================
SITE LOGISTICS PLAN
================================================================

Project: ___________________________________________________

Phase: ____________________________________________________

Date: _____________________________________________________

================================================================

SITE ACCESS:
Main entry: _______________________________________________
Delivery entry: ____________________________________________
Hours: ____________________________________________________
Restrictions: ______________________________________________

STAGING AREAS:
Area 1: _________________ Use: ____________________________
Area 2: _________________ Use: ____________________________
Area 3: _________________ Use: ____________________________

EQUIPMENT:
โ˜ Tower crane Location: _______________________________
โ˜ Mobile crane Access: ________________________________
โ˜ Hoist Location: _______________________________
โ˜ Other: __________________________________________________

TEMPORARY FACILITIES:
โ˜ Field office Location: _______________________________
โ˜ Restrooms (#__) Location: _______________________________
โ˜ Break area Location: _______________________________
โ˜ Storage Location: _______________________________

UTILITIES:
โ˜ Power Source: ________________________________
โ˜ Water Source: ________________________________
โ˜ Data Provider: _______________________________

SECURITY:
โ˜ Fencing Type: __________________________________
โ˜ Lighting
โ˜ Cameras
โ˜ Guards Hours: _________________________________

================================================================

Plan Attached: โ˜ Yes

Prepared By: _______________________ Date: ________________

Approved By: ______________________ Date: ________________

================================================================

Phase Transitionsโ€‹

Update Plan When:โ€‹

  • Major phase changes
  • New subcontractors mobilize
  • Equipment changes
  • Access changes
  • Owner/tenant occupancy

  • Project Startup
  • Safety Requirements
  • Environmental Compliance
  • Subcontractor Coordination

Template provided by support.construction. Good logistics enable efficient construction.