Compliance & Lien Law Procedures Index

Purpose: Mechanics lien rights, preliminary notices, waivers, and compliance
Audience: AR, AP, Project Managers, Legal, Executives


๐Ÿšจ CRITICAL: Protect Your Lien Rightsโ€‹

Mechanics liens are your most powerful tool for getting paid. Missing deadlines = losing rights PERMANENTLY.


Documents in This Sectionโ€‹

DocumentDescriptionPriority
01-preliminary-notice-procedure.mdSending preliminary noticesCRITICAL
02-lien-waiver-management.mdProviding and collecting waiversCRITICAL
03-mechanics-lien-filing.mdWhen and how to file liensCRITICAL
04-stop-notice-procedure.mdStop notice processHigh
05-payment-bond-claims.mdClaims on public work bondsHigh
06-prevailing-wage-compliance.mdCertified payroll requirementsHigh
07-notice-requirements-guide.mdNotice requirements guideReference
08-insurance-requirements.mdInsurance requirementsHigh
09-bonding-guide.mdBonding guideHigh
10-california-compliance-guide.mdComplete CA compliance referenceReference
10-contract-risk-assessment.mdContract risk assessmentMedium
11-bonding-capacity-management.mdBonding capacity managementMedium
12-insurance-claims.mdInsurance claims proceduresMedium
13-insurance-renewal.mdInsurance renewal proceduresMedium
14-credit-risk-assessment.mdCredit risk assessmentMedium

California Lien Law Quick Referenceโ€‹

Key Deadlines (MEMORIZE THESE)โ€‹

ActionDeadlinePenalty for Missing
Preliminary Notice20 days from first workLien limited to work after notice
Mechanics Lien90 days from completionLOSE ALL LIEN RIGHTS
Lawsuit to Enforce90 days from lien recordingLien becomes unenforceable

Who Must Send Preliminary Notice?โ€‹

In California:

  • โœ… Subcontractors - MUST send
  • โœ… Material Suppliers - MUST send
  • โœ… Equipment Lessors - MUST send
  • โŒ Direct (Prime) Contractor - NOT required (but recommended)

Lien Waiver Types (California)โ€‹

TypeWhen Used
Conditional ProgressWith progress payment request
Unconditional ProgressAfter payment received
Conditional FinalWith final payment request
Unconditional FinalAfter final payment received

WARNING: California requires use of statutory waiver forms. Non-compliant forms may be invalid.


Monthly Lien Management Checklistโ€‹

For AR (What We Send)โ€‹

  • Preliminary notices sent for new projects (within 20 days)
  • Conditional waivers sent with pay apps
  • Unconditional waivers sent after payment received
  • Lien deadlines tracked for all projects

For AP (What We Collect)โ€‹

  • Preliminary notices received and logged
  • Conditional waivers collected before payment
  • Unconditional waivers collected after payment
  • All tiers of waivers collected

Lien Timeline Visual (California Private Work)โ€‹

First Work/Materials
|
v
Day 20 -----> Preliminary Notice Due
|
|
|
Project Continues...
|
|
v
Project Completion (or cessation)
|
v
Day 90 -----> Mechanics Lien Must Be Recorded
|
v
Day 90 (from recording) -----> Lawsuit Must Be Filed

Emergency Contactsโ€‹

SituationContact
Lien deadline approachingAR Manager + Legal
Payment issue on public workPM + Legal
Stop notice receivedAP Manager + PM + Legal
Lien filed against our projectPM + Legal + Insurance

  • California Civil Code ยงยง 8000-9566 (Mechanics Lien Law)
  • CFMA Silicon Valley February Lien Law Event
  • Construction Lien Law Guide