Skip to main content
Skip to main content

📑 Submittal Management Guide

Submittals are where projects get delayed. Master the process to keep your schedule on track.

Lead Time is Everything

Know your long-lead items. A 12-week lead time item submitted late = 12 weeks of delay.

What Are Submittals?

Submittals are documents provided by the contractor to demonstrate that materials and equipment meet the design intent. They require architect/engineer review and approval before procurement or installation.

Types of Submittals

TypeExamples
Product DataCut sheets, spec sheets, catalog pages
Shop DrawingsFabrication drawings, coordination drawings
SamplesMaterial samples, color samples, mockups
CertificationsTest reports, LEED documentation
CloseoutO&M manuals, warranties, as-builts

The Submittal Process

1. Identify Required Submittals

At project start:

  • Review specifications for submittal requirements
  • Each spec section lists required submittals
  • Create master submittal log
  • Identify long-lead items immediately

2. Prepare Submittal Schedule

Work backwards from installation:

  1. When must item be installed? (Schedule)
  2. How long is procurement lead time? (Vendor)
  3. How long for approval cycle? (2-4 weeks typical)
  4. When must submittal be submitted? (Calculate)

Example:

  • Installation needed: Week 20
  • Lead time: 8 weeks
  • Approval cycle: 3 weeks
  • Submit by: Week 9 (or earlier)

3. Prepare the Submittal

Include:

  • Submittal cover sheet
  • Specification reference
  • Product data/drawings
  • Highlighted relevant information
  • Contractor review stamp

Contractor Review Before Submission:

  • Verify compliance with specs
  • Check dimensions and quantities
  • Confirm compatibility with other systems
  • Stamp "Approved" or "Approved as Noted"

4. Submit for Review

  • Submit per contract requirements (usually through architect)
  • Include transmittal with required information
  • Note any deviations from specifications
  • Request expedited review if schedule-critical

5. Track the Review

Typical review times:

  • Standard: 10-14 days
  • Complex: 21+ days
  • Resubmittals: 7-14 days

Follow up if:

  • Approaching contract-required review time
  • Item is on critical path
  • No response after expected time

6. Process the Response

Approval Statuses:

StatusMeaningAction
ApprovedProceed with workDistribute and order
Approved as NotedProceed with noted changesIncorporate changes, proceed
Revise and ResubmitNot approvedCorrect and resubmit
RejectedDoes not meet requirementsMajor revision needed
For Record OnlyNo review requiredFile for record

7. Distribute Approved Submittals

Once approved:

  • Distribute to field personnel
  • Provide to subcontractors
  • Include in project documentation
  • Update submittal log

Submittal Log Best Practices

Track these fields:

  • Submittal number
  • Specification section
  • Description
  • Subcontractor responsible
  • Date required (by schedule)
  • Date submitted
  • Date returned
  • Status
  • Resubmittal dates (if any)
  • Comments

Common Submittal Mistakes

Late Submittals

Problem: Submitting after lead time makes installation date impossible

Solution: Create submittal schedule at project start, hold subs accountable

Incomplete Submittals

Problem: Missing information causes rejection or RFIs

Solution: Review specifications carefully, include all required items

Not Reviewing Before Submission

Problem: Contractor stamps "Approved" without checking

Solution: Actually review for spec compliance before stamping

Poor Tracking

Problem: Submittals get lost in the review cycle

Solution: Maintain detailed log, follow up proactively

Substitution Confusion

Problem: Submitting "or equal" without proper documentation

Solution: Follow contract substitution procedures

Long-Lead Items

Identify early and submit immediately:

  • Structural steel (8-16 weeks)
  • Elevators (16-24 weeks)
  • Switchgear (12-20 weeks)
  • Generators (12-20 weeks)
  • Custom millwork (8-12 weeks)
  • Rooftop units (8-12 weeks)
  • Specialty glazing (10-16 weeks)
  • Fire alarm panels (6-10 weeks)
Supply Chain Alert

Current lead times may be longer than historical norms. Verify with suppliers before assuming standard lead times.

Substitutions

When you want to substitute a product:

  1. Check contract — Many prohibit substitutions after bid
  2. Document equivalence — Show it meets all spec requirements
  3. Note differences — Be transparent about any variations
  4. Get approval — Before ordering or installing

Resubmittals

If your submittal is rejected:

  1. Review all comments carefully
  2. Address each comment specifically
  3. Note changes from original
  4. Resubmit promptly
  5. Reference original submittal number

Stay Organized

Free Template: Download our submittal log template to track your submittals.

Automate Tracking: BLDR Pro tracks submittals with automatic reminders, status updates, and deadline alerts so nothing falls through the cracks.