โ RFI Management Guide
How to write effective RFIs, track responses, and protect your project from delays and disputes.
The RFI lifecycle
1
Identify the issue
Find a conflict, ambiguity, or missing information in the contract documents that requires clarification before work can proceed.
2
Draft the RFI
Write a clear, specific question referencing the exact drawing sheets, specification sections, and detail numbers involved.
3
Submit through proper channels
Log in your tracking system, assign a number, and submit per the contract-required process โ typically through the GC to the architect.
4
Track and follow up
Monitor response times against contractual deadlines. Escalate overdue RFIs. Document schedule impact of delayed responses.
5
Incorporate the response
Distribute the answer to the field. If the response changes scope or cost, issue a change order request immediately.
What is an RFI?โ
A Request for Information is a formal question seeking clarification on design documents, specifications, or scope of work. RFI responses become part of the contract documents.
When to Submit an RFIโ
- Conflicting information between drawings
- Missing dimensions or details
- Unclear specifications
- Ambiguous scope
- Field conditions that don't match plans
Don't Use RFIs For
- Requesting scope changes (use PCO/COR)
- Documenting delays (use daily reports)
- General communication (use email)
Writing Effective RFIsโ
Good RFI Structureโ
- Clear subject line โ Specific and searchable
- Reference documents โ Drawing numbers, spec sections
- Specific question โ One issue per RFI
- Suggested solution โ If you have one
- Impact statement โ Schedule or cost if applicable
Example: Good vs Bad RFIโ
โ Bad: "The plumbing doesn't fit. What do we do?"
โ Good: "Per sheet P-201, the 4" waste line at grid B-3 conflicts with the beam shown on S-102. Please confirm which routing is preferred: (A) offset line 6" north, or (B) provide beam penetration detail."
RFI Trackingโ
Essential Fields to Trackโ
| Field | Purpose |
|---|---|
| RFI Number | Unique identifier |
| Date Submitted | Starts response clock |
| Date Due | Per contract (usually 7-10 days) |
| Date Received | When response came |
| Days Open | Tracks delays |
| Subject | Quick reference |
| Status | Open/Pending/Closed |
Response Time Analysisโ
Track average response times by:
- Architect vs Engineer
- RFI complexity
- Project phase
Use this data for delay claims if needed.
When Responses Are Lateโ
- Send follow-up at 7 days
- Escalate at 14 days
- Document impact daily
- Reference in daily reports
- Include in monthly delay logs
Best Practicesโ
- One question per RFI โ Don't bundle issues
- Reference in change orders โ Link COs to triggering RFIs
- Include photos โ Visual context helps
- Suggest solutions โ Shows good faith
- Track everything โ Your RFI log is evidence