Post-Project Review Process
Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Executives
Purpose
Establish a structured process for reviewing completed projects to capture lessons learned and improve future performance.
Post-Project Review vs. Lessons Learned
Lessons Learned: Quick capture of what worked/didn't (already covered)
Post-Project Review: Comprehensive analysis including:
- Financial performance
- Schedule performance
- Client satisfaction
- Team performance
- Process effectiveness
- Estimating accuracy
When to Conduct
Timing:
- After final completion
- Before team disperses
- Ideally within 60 days of closeout
Which Projects:
- All projects over $X (company threshold)
- Problem projects (regardless of size)
- Strategic projects
- New client/market projects
Review Components
1. Financial Analysis
Compare Budget to Actual:
| Category | Budget | Actual | Variance | % |
|---|---|---|---|---|
| Labor | ||||
| Material | ||||
| Subcontract | ||||
| Equipment | ||||
| GCs | ||||
| Other | ||||
| TOTAL |
Profitability:
- Original estimate margin
- Final actual margin
- Variance explained
Change Orders:
- Number of COs
- Total CO value
- % of original contract
- Approval time analysis
Cash Flow:
- DSO during project
- Collection issues
- Retention timing
2. Schedule Analysis
Performance:
- Original duration
- Actual duration
- Variance explained
Key Milestones:
| Milestone | Planned | Actual | Variance |
|---|---|---|---|
Delay Analysis:
- Owner-caused delays
- Contractor delays
- Excusable delays
- Recovery efforts
3. Quality Analysis
Metrics:
- First-time pass rate
- Punch list items/1000 SF
- Rework cost %
- Warranty callbacks
Issues:
- Major quality issues
- Root causes
- Prevention for future
4. Safety Analysis
Metrics:
- Hours worked
- Recordable incidents
- Near misses reported
- TRIR
Issues:
- Incidents that occurred
- Root causes
- Prevention measures
5. Client Satisfaction
Feedback:
- Formal survey results
- Informal feedback
- Relationship status
- Repeat business likelihood
Issues:
- Complaints received
- Resolution effectiveness
- Areas for improvement
6. Estimating Accuracy
By Category:
| Category | Estimated | Actual | Accuracy % |
|---|---|---|---|
| Labor hours | |||
| Material costs | |||
| Sub costs | |||
| Equipment | |||
| GCs |
Update Estimating Data:
- Productivity rates
- Material pricing
- Subcontractor costs
- GC percentages
Post-Project Review Meeting
Attendees:
- Project Manager
- Superintendent
- Estimator (original)
- Operations/Executive
- Key team members
Agenda:
-
Project Summary (10 min)
- Scope overview
- Key challenges
- Overall assessment
-
Financial Review (20 min)
- Budget vs. actual
- Variance analysis
- Change order review
-
Schedule Review (15 min)
- Performance analysis
- Delay causes
- Recovery efforts
-
Quality/Safety (10 min)
- Metrics review
- Issues and causes
-
Client Feedback (10 min)
- Survey results
- Relationship status
-
Lessons Learned (20 min)
- What worked well
- What didn't work
- Recommendations
-
Action Items (15 min)
- Process improvements
- Training needs
- System updates
- Knowledge sharing
Post-Project Review Report
================================================================
POST-PROJECT REVIEW REPORT
================================================================
Project: ___________________________________________________
Date: _____________________________________________________
Reviewed By: _______________________________________________
================================================================
EXECUTIVE SUMMARY:
Overall Project Assessment: ☐ Excellent ☐ Good ☐ Fair ☐ Poor
Key Achievements:
___________________________________________________________
Key Challenges:
___________________________________________________________
________________________________________________________________
FINANCIAL SUMMARY:
Original Contract: $____________________
Final Contract: $____________________
Change Order %: ________%
Estimated Margin: ________%
Actual Margin: ________%
Variance: ________%
________________________________________________________________
SCHEDULE SUMMARY:
Original Duration: ________ days/months
Actual Duration: ________ days/months
Variance: ________ days
Reason(s):
___________________________________________________________
________________________________________________________________
QUALITY/SAFETY:
Punch Items per 1000 SF: ________
Rework Cost %: ________%
TRIR: ________
Incidents: ________
________________________________________________________________
CLIENT SATISFACTION:
Overall Rating: ____ / 5
Would Recommend: ☐ Yes ☐ No
Repeat Business Expected: ☐ Yes ☐ No ☐ Maybe
________________________________________________________________
KEY LESSONS:
What Worked Well:
1. ________________________________________________________
2. ________________________________________________________
3. ________________________________________________________
What Didn't Work:
1. ________________________________________________________
2. ________________________________________________________
3. ________________________________________________________
________________________________________________________________
RECOMMENDATIONS:
For Future Projects:
1. ________________________________________________________
2. ________________________________________________________
For Estimating:
1. ________________________________________________________
2. ________________________________________________________
For Operations:
1. ________________________________________________________
2. ________________________________________________________
________________________________________________________________
ACTION ITEMS:
| Action | Owner | Due Date |
|--------|-------|----------|
| | | |
| | | |
| | | |
================================================================
Reviewed By: _______________________ Date: _________________
Approved By: ______________________ Date: _________________
================================================================
Knowledge Transfer
Share Learnings:
- Company-wide lessons learned database
- Monthly PM meetings
- Training sessions
- Estimating updates
What to Share:
- Productivity data
- Successful methods
- Issues to avoid
- Client preferences
- Subcontractor performance
Client Satisfaction Survey
Survey Questions:
- Overall satisfaction (1-5)
- Communication quality (1-5)
- Responsiveness (1-5)
- Quality of work (1-5)
- Schedule performance (1-5)
- Problem resolution (1-5)
- Would you hire us again?
- Would you recommend us?
- What did we do well?
- What could we improve?
Related Documents
- Lessons Learned
- Financial Closeout
- Warranty Administration
- Estimating Standards
Template provided by support.construction. Learn from every project.