Financial Closeout Procedure
Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: Project Managers, Accounting
Purpose
Establish procedures for completing project financial closeout to ensure all costs are captured, revenues collected, and profitability calculated.
Financial Closeout Timeline
| Activity | Timing |
|---|---|
| Final change orders | Before final billing |
| Sub final payments | Within 30 days of completion |
| Final pay application | Per contract |
| Retention collection | Per contract |
| Cost reconciliation | Within 60 days |
| Profit/loss analysis | Within 90 days |
| Job closeout | Within 120 days |
Financial Closeout Steps
Step 1: Process Final Change Orders
Before Final Billing:
- All change orders submitted
- All change orders approved
- All change orders billed
- No pending changes
Step 2: Finalize Subcontractor Payments
For Each Subcontractor:
- Final pay application received
- Punch list complete
- Backcharges processed
- Final lien waiver collected
- Final payment processed
Step 3: Finalize Vendor Payments
For Each Vendor:
- All invoices received
- All invoices paid
- Credits applied
- Accounts closed
Step 4: Submit Final Pay Application
Final Billing Includes:
- All remaining contract work
- All approved change orders
- Retention release request
- Final lien waivers
Step 5: Collect Final Payment and Retention
Track:
- Final payment received
- Retention received
- All funds collected
Step 6: Reconcile Job Costs
Compare:
- Budget vs. actual (by cost code)
- Identify variances
- Explain significant differences
- Document lessons learned
Step 7: Calculate Final Profit/Loss
Financial Summary:
- Total contract value
- Total costs
- Gross profit
- Gross margin %
Step 8: Close Project in System
Final Actions:
- Close all purchase orders
- Close job in accounting
- Archive project files
- Complete closeout report
Job Cost Reconciliation
Cost Comparison:
| Cost Code | Budget | Actual | Variance | % |
|---|---|---|---|---|
| Labor | ||||
| Material | ||||
| Equipment | ||||
| Subcontract | ||||
| Other | ||||
| TOTAL |
Variance Analysis:
- Identify major variances (> 5%)
- Determine causes
- Document for future estimates
Financial Closeout Checklist
================================================================
PROJECT FINANCIAL CLOSEOUT CHECKLIST
================================================================
Project: _____________________ Project #: ____________________
PM: _________________________ Close Date: ___________________
================================================================
CHANGE ORDERS:
☐ All COs submitted
☐ All COs approved
☐ All COs billed
☐ Final CO log complete
SUBCONTRACTORS:
☐ All final pay apps processed
☐ All backcharges processed
☐ All final lien waivers collected
☐ All final payments made
VENDORS/SUPPLIERS:
☐ All invoices received
☐ All invoices paid
☐ All credits applied
BILLING:
☐ Final pay application submitted
☐ Final payment received
☐ Retention received
☐ All funds collected
JOB COSTS:
☐ All costs posted
☐ All time charged
☐ Cost reconciliation complete
☐ Variances analyzed
FINANCIAL:
☐ Profit/loss calculated
☐ Margin % calculated
☐ Closeout report complete
ADMINISTRATIVE:
☐ Job closed in accounting system
☐ POs closed
☐ Files archived
☐ Lessons learned documented
================================================================
FINAL PROJECT FINANCIAL SUMMARY:
Original Contract: $____________________
Change Orders: $____________________
Final Contract Value: $____________________
Total Costs: $____________________
Gross Profit: $____________________
Gross Margin: ________%
================================================================
PM Signature: _______________________ Date: _________________
Accounting: _________________________ Date: _________________
================================================================
Profit/Loss Analysis
Final Project P&L:
CONTRACT REVENUE:
Original Contract $__________
Change Orders $__________
Total Revenue $__________
DIRECT COSTS:
Labor $__________
Material $__________
Equipment $__________
Subcontracts $__________
Other Direct $__________
Total Direct Costs $__________
GROSS PROFIT $__________
GROSS MARGIN ________%
INDIRECT COSTS:
General Conditions $__________
Warranty Reserve $__________
Total Indirect $__________
NET PROFIT $__________
NET MARGIN ________%
Related Documents
- Final Pay Application
- Retention Release Request
- Sub Final Payment Process
- Lessons Learned Report
Template provided by support.construction. Customize with your company information.