Subcontractor Payment Process
Document Type: Procedure
Version: 1.0
Last Updated: February 2026
Distribute To: AP Team, Project Managers
Purpose
Establish a consistent process for receiving, reviewing, and processing subcontractor pay applications while ensuring compliance with lien waiver requirements and contract terms.
Payment Flow Overview
Sub Pay App → PM Review → Approval → Lien Waiver Collection →
AP Processing → Check Run → Distribution
Subcontractor Pay Application Requirements
What Subs Must Submit
Required with Every Pay App:
- Completed pay application form
- Schedule of Values (if applicable)
- Conditional Lien Waiver (current period)
- Unconditional Lien Waiver (previous period paid)
- Lower-tier lien waivers (their subs/suppliers)
If Prevailing Wage Project:
- Certified payroll for period
- Fringe benefit statements
If Stored Materials:
- Invoices for stored materials
- Photos of materials
- Proof of insurance coverage
For Final Payment:
- Unconditional Final Lien Waiver
- Warranty documentation
- O&M manuals (if required)
- As-built markups (if required)
- Final certified payroll
Step-by-Step Process
Step 1: Pay App Receipt
Who: AP or PM
When: Per contract terms (typically monthly)
-
Log receipt of pay application
-
Check for completeness:
- All required documents included
- Correct forms used
- Period matches billing cycle
-
If incomplete:
- Notify sub immediately
- List missing items
- Set deadline for resubmission
Step 2: PM Review and Approval
Who: Project Manager
When: Within 5 business days of receipt
Review Checklist:
Verify Work Completed
- Percentages match actual progress
- Work quality acceptable
- No incomplete/defective work
- Stored materials properly documented
Check Contract Compliance
- Amount within contract/commitment
- Change orders properly documented
- Insurance current
- Certified payroll compliant (if required)
Verify Calculations
- Math is correct
- Retainage calculated properly
- Previous payments deducted correctly
- Change orders applied correctly
Approve or Adjust
- Sign approved pay app
- Or note adjustments with explanation
- Return adjusted pay app to sub for revised submission
Step 3: Lien Waiver Verification
CRITICAL: Do not process payment without proper lien waivers.
Required Waivers:
| Payment Type | From Sub | From Sub's Subs/Suppliers |
|---|---|---|
| Progress Payment | Conditional (current period) + Unconditional (previous period) | Same |
| Final Payment | Unconditional Final | Unconditional Final |
Waiver Review:
- Correct form used (state-specific)
- Dates match payment period
- Amounts match payment
- Properly signed
- Notarized (if required)
- Cover all tiers identified
If Waivers Missing:
- Contact sub immediately
- Hold payment until received
- Document communication
- Set firm deadline
Step 4: AP Processing
Who: AP Department
When: After PM approval and lien waiver verification
-
Enter in System:
- Vendor (subcontractor)
- Invoice number/pay app number
- Amount approved
- Project and cost codes
- Payment terms
- Due date
-
Three-Way Match:
- Subcontract/commitment (what's owed)
- Approved pay app (what's billed)
- PM approval (what's approved to pay)
-
Schedule Payment:
- Per contract terms
- Coordinate with cash flow
- Note in check run schedule
Step 5: Payment Processing
Check Run Schedule:
- Weekly check runs (typical)
- Friday processing, Tuesday mail (typical)
Payment Methods:
- Check (most common)
- ACH/EFT (if set up)
- Wire (large amounts, expedited)
Include with Payment:
- Pay app copy or remittance advice
- Unconditional waiver request (for next period)
Step 6: Payment Distribution and Tracking
After Payment Sent:
- Update sub payment history
- Log check number and date
- Request unconditional waiver
- Update commitment balance
- File all documentation
Pay-When-Paid vs. Pay-If-Paid
Understanding Your Contract Terms
Pay-When-Paid:
- Common clause
- You must pay sub within reasonable time after you're paid
- Sets timing, but sub is eventually entitled to payment
Pay-If-Paid:
- More restrictive
- Your payment to sub is conditioned on you being paid
- May not be enforceable in all jurisdictions
- Consult legal counsel
Best Practice
- Pay subs promptly regardless of owner payment
- Maintain good relationships
- Sub payment delays create lien exposure
Subcontractor Payment Problems
Problem: Disputed Work
Process:
- Document specific issues in writing
- Notify sub within contract timeframes
- Withhold only disputed portion
- Pay undisputed amounts
- Work toward resolution
- Document all communication
Problem: Missing Lien Waivers
Process:
- Contact sub immediately
- Explain lien exposure
- Set firm deadline (2-3 days)
- Hold payment until received
- Escalate if not resolved
Problem: Certified Payroll Issues
Process:
- Identify specific discrepancy
- Notify sub in writing
- Request corrected CPR
- May need to hold payment
- Report to awarding agency if required
Problem: Insurance Lapse
Process:
- Immediately notify sub
- Stop sub's work until resolved
- Request updated certificate
- Hold payment until current
- Backcharge for coverage gaps (per contract)
Retainage Management
Holding Retainage
- Per subcontract terms (typically 5-10%)
- Calculate on each pay app
- Track cumulative retainage
Releasing Retainage
Release when:
- Sub's work complete
- Punch list items resolved
- Final lien waivers received
- Warranties provided
- As-builts/closeout docs submitted
Partial Release:
- May release portion at substantial completion
- Hold final retainage until all requirements met
Joint Check Agreements
When to Use
- Sub has payment issues with their suppliers
- Supplier sends preliminary notice
- Protecting against lien exposure
Process
- Receive request (from sub or supplier)
- Verify amounts and legitimacy
- Issue check payable to:
- "Subcontractor Name AND Supplier Name"
- Both parties must endorse
- Get lien waivers from both
Subcontractor Payment Checklist
Before processing payment:
- Pay app complete and accurate
- PM reviewed and approved
- Work verified complete and acceptable
- Change orders properly documented
- Retainage calculated correctly
- Conditional waiver received (current)
- Unconditional waiver received (previous)
- Lower-tier waivers collected
- Insurance current
- Certified payroll verified (if required)
- Entered in accounting system
- Three-way match completed
- Scheduled for payment
Metrics to Track
| Metric | Target | Frequency |
|---|---|---|
| Payment Timeliness | Per contract terms | Monthly |
| Lien Waiver Collection Rate | 100% | Monthly |
| Disputes Outstanding | < 5% of payments | Monthly |
| Sub Satisfaction | Regular communication | Ongoing |
Related Documents
- Subcontract Agreement Template
- Lien Waiver Forms (State-Specific)
- Certified Payroll Compliance Guide
- Backcharge Procedure
- Vendor Setup Procedure
Software Integration
BLDR Pro Features:
- Track sub percentages in field
- Photo documentation of work
- Digital pay app submission
- Waiver tracking dashboard
- Integration with accounting