Skip to main content
Skip to main content

❓ RFI Process Playbook

Get design clarifications documented and answered promptly. An unanswered RFI is a ticking time bomb — it either delays work or forces you to guess, both of which cost money.


Why the RFI Process Matters

ScenarioWithout RFI ProcessWith RFI Process
Conflicting details on drawingsGuess and hope you're rightDocument the conflict, get a definitive answer
Missing informationProceed with assumptionsAssumptions documented, answer recorded
Design error discoveredBuild it wrong, then reworkCatch it before construction, architect issues fix
Dispute over direction"We told you verbally"Written record of question and answer
Schedule delay from late answerNo documentation of impactRFI log proves delay was caused by late response

Roles and Responsibilities

RoleResponsibilities
Field PersonnelIdentify conflicts, missing info, or questions — report to project engineer
Project EngineerDraft RFI, review with PM, submit, track, distribute response
Project ManagerReview RFIs before submission, escalate overdue responses, assess cost/schedule impact
Architect / EngineerRespond within contract timeframe, issue revised drawings if needed
SubcontractorsSubmit questions through GC (not directly to architect), implement responses

Step-by-Step Process

Step 1: Identify the Issue

Valid reasons for an RFI:

  • Conflicting information between drawings, specs, or details
  • Missing dimensions, details, or specifications
  • Ambiguous language in specifications
  • Field conditions that differ from drawings
  • Constructability concerns
  • Substitution requests (sometimes handled separately)

NOT valid RFI topics (handle differently):

  • Requests for additional work → Change Order
  • Claims for extra cost → Change Order Request
  • Schedule changes → Schedule revision
  • Safety concerns → Safety report
  • "Can we do it this way instead?" without a design issue → Proposal

Step 2: Draft the RFI

Every RFI must include:

ElementDetailsExample
RFI numberSequential project numberRFI-042
Date submittedDate sent to reviewer02/12/2026
Subject lineClear, specific subject"Conflict — Structural beam depth at Grid C/3 (S-201 vs. S-301)"
ReferenceDrawing/spec/detail numberDrawing S-201, Detail 3; Drawing S-301, Section A
QuestionClear, specific question"S-201 shows W12x26 beam at Grid C/3. S-301 shows W14x30 at same location. Which is correct?"
Suggested resolutionYour proposed answer"We recommend W14x30 per S-301 as it appears to be the latest design intent"
ImpactSchedule/cost impact if not answered"This beam is scheduled for fabrication 03/01. Late response may delay steel erection by 2 weeks."
Required response dateWhen you need the answer02/26/2026 (14 calendar days per contract)
Always Suggest a Resolution

Including a suggested answer accomplishes two things: (1) it shows you've thought about it, and (2) it gives the architect an easy path to a quick response — they can simply agree or provide an alternative.

Step 3: Internal Review

Before submitting:

  1. PM reviews — Is the question clear? Is it actually an RFI or should it be a different document?
  2. Check for duplicates — Has this been asked before? Check the RFI log.
  3. Combine related questions — If you have 3 questions about the same detail, combine them into one RFI with sub-questions.
  4. Verify references — Are the drawing/spec references correct?

Step 4: Submit the RFI

  1. Log in the RFI tracking system
  2. Submit per contract requirements (email, project management platform, or hard copy)
  3. Confirm receipt (request read receipt or acknowledgment)
  4. Note the contract review period (typically 7–14 calendar days)
  5. Set follow-up reminder

Step 5: Track the Response

DayAction
Day 0Submitted — confirm receipt
Day 5If no acknowledgment, follow up
Day 10If nearing deadline, send reminder with impact statement
Day 14If overdue, formal written notice — "RFI-042 is past the X-day response period per Section Y of the contract"
Day 21+Escalate to owner, document schedule impact

Step 6: Process the Response

When the response arrives:

  1. Log the response — Date received, from whom
  2. Review for completeness — Does it actually answer the question?
  3. Check for cost/schedule impact — Does the answer change scope, cost, or schedule?
  4. Distribute to affected parties — Foreman, superintendent, subcontractors
  5. Update drawings — Mark up field set of drawings with the response
  6. If incomplete or unclear — Follow up or submit a new RFI referencing the original

If the response changes scope or adds cost:

  • Do NOT proceed without a change order
  • Issue a COR (Change Order Request) referencing the RFI
  • Document the cost and schedule impact

Writing Better RFIs

Good vs. Bad Examples

Bad RFI:

"The beam doesn't work. What should we do?"

Good RFI:

"RFI-042: Conflict — Beam Size at Grid C/3

Drawing S-201, Detail 3 shows a W12x26 beam at Grid C/3. Drawing S-301, Section A shows a W14x30 at the same location. Structural calculations (if available) should clarify the design intent.

Suggested Resolution: Install W14x30 per S-301, which appears to reflect the latest design revision.

Impact: Steel fabrication for this area is scheduled to begin 03/01/2026. Response needed by 02/26/2026 to avoid a 2-week delay to steel erection."

RFI Writing Checklist

  • Subject line is specific (not "Question about structural")
  • Drawing and spec references are correct
  • Question is clear — a yes/no or specific answer is possible
  • Only ONE topic per RFI (don't bundle unrelated questions)
  • Suggested resolution is included
  • Impact (cost/schedule) is noted
  • Response deadline is stated

Common Mistakes

MistakeConsequenceFix
Vague questionsVague answers — another round tripBe specific: reference exact drawings, locations, dimensions
Too many RFIsArchitect gets overwhelmed, responses slow downCombine related questions, resolve simple issues in meetings
Not tracking responsesOverdue answers go unnoticedLog every RFI, set reminders, follow up proactively
No impact statementArchitect doesn't prioritize urgent RFIsAlways state the schedule and cost impact of a late response
Proceeding without an answerBuild it wrong, then reworkStop work or build to your suggested resolution (document the assumption)
Verbal answers not documented"We never said that"If architect answers verbally, send written confirmation: "Per our conversation on 02/12, we understand the answer is..."

Metrics

MetricTargetFrequency
RFI response time (average)Within contract periodMonthly
Overdue RFIsZero overdue over 7 days past contract periodWeekly
RFIs per monthTrack trend — increasing may signal drawing quality issuesMonthly
Impact RFIs (cost/schedule)Tracked and linked to CORsPer occurrence

ResourceLink
RFI GeneratorGenerate RFI
RFI Log TrackerRFI Log
RFI Management GuideFull Guide
Change Order PlaybookChange Order Workflow