Skip to main content
Skip to main content

📋 Daily Field Reporting Playbook

Document crew hours, work completed, weather conditions, and site activities at the end of each day. Your daily report is your single most important project document — it creates the legal record of everything that happened on your jobsite.


Why Daily Reports Matter

ScenarioWithout Daily ReportsWith Daily Reports
Delay claim disputeNo evidence of actual conditionsDay-by-day record with photos
Labor productivity question"I think we had 6 guys that day"Exact headcount, hours, and cost codes
Change order negotiationHe-said / she-saidWritten record of conditions, directions, and impacts
OSHA investigationScrambling to reconstruct timelineDocumented safety conditions and crew activities
Contract dispute / litigationWeak case, missing factsDaily contemporaneous record (strongest evidence)
The Legal Gold Standard

Courts give heavy weight to daily reports because they are "contemporaneous records" — documents created at the time events occurred, not reconstructed later. A daily report written at 4:30 PM is 10x more credible than a statement written 6 months later during litigation.


Roles and Responsibilities

RoleResponsibilities
ForemanDocument own crew's hours, work completed, and cost codes daily
SuperintendentCompile all foremen reports into project daily report, add site-wide observations
Project ManagerReview daily reports for accuracy, flag issues, ensure distribution
Project EngineerMaintain daily report archive, cross-reference with schedule

What to Document Every Day

Weather and Conditions

FieldDetailsWhy It Matters
Temperature (AM/PM)High and low for the dayConcrete curing, heat illness, cold stress triggers
PrecipitationType, duration, accumulationDelay documentation, earthwork impacts
WindSpeed and directionCrane operations, roofing work, fall protection
Ground conditionsDry, wet, muddy, frozenEquipment access, earthwork, safety
VisibilityGood, fog, dust, smokeCrane operations, equipment movement
Work impactFull day, partial day, lost daySchedule and delay tracking

Crew and Labor

FieldDetailsWhy It Matters
Workers by tradeName, trade, companyWho was on site
Hours by workerStart, end, total hours, OTPayroll, labor productivity, certified payroll
Cost codesWhat each worker/crew worked onJob costing, productivity analysis
Headcount summaryTotal workers on site by companyManpower loading vs. plan

Work Completed

FieldDetailsWhy It Matters
Activities by areaWhat was done, where, how muchProgress tracking, percent complete
Quantities installedLF, SF, CY, EA — measurable unitsProductivity rates, pay application support
Schedule activitiesWhat schedule activities were workedSchedule update support
Work NOT completedWhat was planned but not done, and whyDelay documentation

Equipment

FieldDetailsWhy It Matters
Equipment on siteType, ID/serial, companyUtilization tracking, rental costs
Equipment hoursActive hours, idle hoursCost tracking, rental justification
DeliveriesWhat arrived, from whom, conditionMaterial tracking, damage claims

Visitors and Inspections

FieldDetailsWhy It Matters
VisitorsName, company, purpose, time in/outSecurity, liability
InspectionsWho inspected, what was inspected, resultCompliance, quality documentation
Owner/architect visitsWho visited, what was discussedDirection documentation

Issues and Conversations

FieldDetailsWhy It Matters
Verbal directionsWho said what, whenChange order support
Conflicts or problemsWhat happened, how it was resolvedDispute documentation
Safety observationsHazards noted, actions takenSafety culture documentation
Delays or impactsWhat was impacted, cause, durationDelay claim support

Daily Report Workflow

End-of-Day Process (30–45 Minutes)

3:30 PM  Foremen submit crew hours and work completed to Superintendent
3:45 PM Superintendent walks the site — verify work, note conditions
4:00 PM Take end-of-day photos (5–10 minimum)
4:15 PM Complete the daily report
4:30 PM Review, finalize, and distribute

Step-by-Step

  1. Collect foremen input — Each foreman reports crew hours, work completed, and cost codes
  2. Walk the site — Verify work in place, check conditions, note any issues
  3. Take photos — At least 5–10 photos documenting today's progress (see photo guide below)
  4. Write the narrative — Factual description of the day's activities, issues, and conversations
  5. Review for completeness — Check every section, don't leave blanks
  6. Distribute — Send to PM, owner rep, and file copy per contract requirements

Photo Documentation Guide

Daily Minimums (5–10 Photos)

ShotWhat to CaptureTip
OverviewWide shot of the whole site from a consistent locationSame angle every day = progress sequence
Active work areasEach area where work was performed todayInclude workers for scale, show progress
Completed workClose-ups of today's finished workBefore backfill, before cover-up
DeliveriesMaterial deliveries, staging areasCapture condition on arrival
Weather/conditionsSky, ground conditions, standing waterSupports delay documentation

When to Take Extra Photos

  • Any verbal direction — Photo of what they're pointing at
  • Changed conditions — Unexpected site conditions, differing conditions
  • Damage or defects — Equipment damage, defective materials, punch items
  • Safety observations — Good and bad safety conditions
  • Before concrete pour — Rebar, formwork, embedded items (before they're covered)
  • Before backfill — Underground utilities, waterproofing (before they're buried)
Photo Naming

Include the date, location, and subject in photo filenames or descriptions: 2026-02-12_Bldg-A_Level3_rebar-inspection.jpg — not IMG_4823.jpg.


Writing Effective Narratives

Good vs. Bad Narrative Examples

Bad:

"Worked on building. Poured concrete. Weather was OK."

Good:

"Crew of 8 (4 laborers, 2 cement masons, 1 pump operator, 1 foreman) placed 45 CY of 4000 PSI concrete for the Level 2 east wing elevated slab, grids E-H / 1-4. Pump truck arrived at 7:30 AM, pour began at 8:00 AM, completed at 1:30 PM. Finish work continued until 3:30 PM. Temperature 72°F at pour start, 81°F at completion. No rain. Concrete tested at 5.5" slump, 4.2% air. Two cylinders pulled for 7-day and 28-day breaks. No safety incidents."

What Makes a Good Narrative

  • Specific quantities — 45 CY, not "some concrete"
  • Specific locations — Grid E-H / 1-4, not "east side"
  • Specific times — 8:00 AM to 1:30 PM, not "most of the day"
  • Crew composition — 4 laborers + 2 cement masons, not "the crew"
  • Conditions and results — Slump, air content, test results
  • Safety note — Always mention safety status (incidents, near-misses, or "no incidents")

Common Mistakes

MistakeRiskFix
Skipping a dayGaps in the record destroy credibilityNever miss a day — even on rain days, document the rain
Vague descriptionsUseless in disputesBe specific: quantities, locations, times, names
No photos"Pics or it didn't happen"Minimum 5 photos per day — make it habit
Not noting delaysCan't prove delay claims laterAlways document what wasn't done and why
Including opinionsCan be used against youStick to facts: "Rain from 10 AM to 2 PM, earthwork suspended" not "GC should have planned better"
Filing lateLoses contemporaneous credibilityComplete and distribute same day
Not documenting conversationsVerbal directions are forgotten"At 2 PM, architect directed us to revise header height from 8' to 8'-6"

Distribution and Retention

RecipientWhenMethod
Project ManagerSame dayEmail / project management software
Owner RepresentativePer contract (often daily)Email / project management software
GC (if subcontractor)Per contractEmail / project management software
Project fileSame dayDigital archive + backup

Retention: Duration of project + statute of limitations (varies by state, typically 4–10 years). When in doubt, keep them for 10 years.


ResourceLink
Daily Report GeneratorGenerate Report
Daily Reporting GuideFull Guide
Photo Documentation GuidePhoto Guide
BLDR Pro (Digital Daily Reports)bldr.pro