📝 Change Order Workflow Playbook
Document scope changes, get approvals, and track cost/schedule impacts properly. The #1 rule of change orders: document first, execute second. Work performed without written authorization is work you may never get paid for.
Why Change Order Management Matters
| Without a Process | With a Process |
|---|---|
| "We told you verbally" — disputed verbal directions | Written COR with documented direction |
| Performed extra work with no approval — unpaid | Work authorized before execution |
| No cost backup — GC disputes your pricing | Detailed pricing with backup documentation |
| Schedule impact ignored — you absorb the delay | Documented time impact included in COR |
| Lump-sum negotiation with no leverage | Cost breakdown supports fair negotiation |
Never perform extra work without written authorization. If you're told verbally, confirm in writing before starting. If you're forced to start due to schedule pressure, send a written notice of intent to claim the cost within 24 hours.
Roles and Responsibilities
| Role | Responsibilities |
|---|---|
| Field Personnel | Identify changed conditions, document immediately (photos, notes), notify foreman |
| Foreman | Report potential change to superintendent, track extra labor/equipment/materials separately |
| Superintendent | Notify PM of potential change, document field conditions, review COR for accuracy |
| Project Manager | Draft COR, prepare pricing, submit to owner/GC, negotiate, track approval |
| Project Engineer | Maintain change order log, assemble backup documentation, track status |
| Estimator | Prepare detailed cost estimates for COR pricing |
Types of Changes
| Type | Trigger | Example |
|---|---|---|
| Owner-directed change | Owner requests additional or different work | "Add 6 electrical outlets to Conference Room B" |
| Design error / omission | Drawings or specs are wrong or incomplete | Structural conflict discovered — RFI confirms redesign needed |
| Differing site conditions | Actual conditions differ from contract documents | Underground rock not shown on geotech report |
| Regulatory change | Building code or permit requirement changes | Inspector requires additional fire stopping not in original scope |
| Schedule acceleration | Owner requests earlier completion | "We need to move in 2 weeks earlier" |
| Scope reduction (credit) | Owner removes work from your scope | "Delete the interior painting from your contract" |
Step-by-Step Process
Step 1: Identify the Change (Immediately)
The moment anyone on your team identifies potential extra work:
- Stop and evaluate — Is this in our contract scope? Check the contract documents.
- Do NOT proceed with the extra work unless there's a safety or emergency reason
- Notify the superintendent and PM — immediately, verbally + in writing
- Document the condition — Photos, measurements, descriptions
- Start tracking costs separately — Use a separate cost code for the potential change
Step 2: Send Written Notice (Within 24–48 Hours)
Check your contract for notice requirements. Most contracts require written notice within a specific timeframe (often 7–21 days). Missing the notice deadline can waive your right to the change order.
Written notice includes:
- Date
- Contract and project reference
- Description of the changed condition or direction
- Contract provision requiring the change (if applicable)
- Statement of intent to request a change order
- Request for direction on how to proceed
Example notice:
"This letter serves as notice that on 02/12/2026, during excavation at Grid B/4, we encountered rock at elevation 98.5'. The geotechnical report (dated 08/2025) indicates soil to elevation 95.0'. This constitutes a differing site condition per Section 4.3 of the contract. We request direction on how to proceed and reserve our right to submit a change order for the additional cost and time required for rock removal."
Step 3: Document Everything
| What to Document | How | Why |
|---|---|---|
| Photos of the condition | Before, during, and after | Visual evidence of the change |
| Daily reports noting the change | Separate entries for change work | Contemporaneous record |
| Extra labor hours | Separate time cards or cost codes | Cost backup |
| Extra equipment | Usage logs with hours | Cost backup |
| Extra materials | Receipts, delivery tickets, invoices | Cost backup |
| Written directions received | Emails, RFI responses, meeting minutes | Proof of direction |
| Schedule impact | Updated schedule showing delay/acceleration | Time extension support |
Step 4: Prepare the Change Order Request (COR)
COR Package includes:
- Cover letter — Summary of the change, contract reference, total cost and time requested
- Detailed cost breakdown:
| Cost Category | Calculation Method |
|---|---|
| Labor | Hours × rate (including burden) per worker/trade |
| Materials | Quantity × unit cost (with supplier quotes or invoices) |
| Equipment | Hours × rate (rental rate or internal rate) |
| Subcontractor costs | Sub's quotes or invoices (with your markup) |
| Overhead | Per contract (typically 10–15% of direct costs) |
| Profit | Per contract (typically 5–10% of direct costs) |
| Bond premium | If bonded (typically 1–2% of change amount) |
| Total | Sum of all categories |
- Backup documentation — Time cards, material receipts, equipment logs, photos, RFI responses
- Schedule impact analysis — Days of delay or acceleration, revised milestone dates
- Markup substantiation — Reference the contract markup provisions
Step 5: Submit and Track
- Submit COR per contract requirements (usually to GC or owner's representative)
- Log in the change order tracking system
- Request written acknowledgment of receipt
- Set follow-up reminders:
- Day 7: Follow up if no response
- Day 14: Formal follow-up with schedule impact warning
- Day 21+: Escalate per contract dispute provisions
Step 6: Negotiate
| Approach | When to Use |
|---|---|
| Agree on price before work | Preferred — no risk of non-payment |
| T&M with not-to-exceed | When scope is unclear — track actual costs up to a cap |
| T&M open-ended | Emergency or undefined scope — agree on rates, track actual costs |
| Proceed under protest | When forced to start before agreement — document everything, reserve rights |
Negotiation tips:
- Start with your detailed backup — let the numbers speak
- Be prepared to explain every line item
- Know your contract markup rates before negotiating
- Don't accept "we'll work it out later" — get it in writing
- If you can't agree on price, agree on a method (T&M) and track it
Step 7: Execute the Change Order
Once approved:
- Receive signed change order document
- Verify it matches what was agreed (scope, cost, time)
- Distribute to field — superintendent, foreman, affected subs
- Update the schedule of values
- Include in the next pay application
- Update project budget and schedule
Change Order Log
Track every potential and actual change:
| # | Description | Date Identified | Notice Sent | COR Submitted | Amount | Status | CO # |
|---|---|---|---|---|---|---|---|
| PCO-001 | Rock at Grid B/4 | 02/12 | 02/12 | 02/20 | $28,500 | Under Review | — |
| PCO-002 | Add outlets to Conf Room B | 02/14 | N/A (owner directed) | 02/18 | $4,200 | Approved | CO-003 |
| PCO-003 | RFI-042 beam redesign | 02/15 | 02/15 | Pending | TBD | Pricing | — |
Common Mistakes
| Mistake | Consequence | Fix |
|---|---|---|
| Performing work before approval | Owner can refuse to pay | Get written authorization first — always |
| Missing the notice deadline | Waive your right to the change | Know your notice requirements, send notice within 24 hours |
| Verbal agreements | "That's not what we agreed to" | Confirm everything in writing |
| Incomplete cost backup | GC disputes your numbers | Track every hour, receipt, and invoice from day one |
| Ignoring schedule impact | You absorb the delay | Always include time extension request with cost |
| Bundling unrelated changes | One disputed item holds up the whole package | One COR per change — keep them separate |
| Not tracking pending changes | Lost revenue | Maintain a change order log, review weekly |
Metrics
| Metric | Target | Frequency |
|---|---|---|
| Notice sent within 48 hours | 100% | Per occurrence |
| COR submitted within 14 days of direction | over 90% | Per occurrence |
| Approval rate | over 80% of submitted CORs | Monthly |
| Average approval time | under 30 days | Monthly |
| Pending COR value | Tracked and reported | Weekly |
| Collection rate on approved COs | 100% collected | Monthly |
Related Resources
| Resource | Link |
|---|---|
| Change Order Request Generator | Generate COR |
| Change Order Log Tracker | CO Log |
| Change Order Guide | Full Guide |
| T&M Ticket Playbook | T&M Workflow |
| RFI Process Playbook | RFI Process |