📤 Submittal Management Playbook

Track shop drawings, product data, and samples through the approval cycle. Late or rejected submittals are one of the top causes of construction delays — this playbook keeps them moving.


Why Submittal Management Matters

ImpactPoor Submittal ManagementGood Submittal Management
ScheduleDelayed approvals = delayed procurement = delayed workSubmittals approved ahead of need dates
CostRush orders from late submittals, rework from unapproved productsMaterials ordered on time at best price
QualityWrong products installed, expensive reworkCorrect products confirmed before ordering
Disputes"We never approved that" — contract disputesFull documentation of every approval

Roles and Responsibilities

RoleResponsibilities
Project EngineerCreate submittal schedule, prepare packages, log and track all submittals, distribute responses
Project ManagerReview submittals before sending, monitor schedule, escalate late reviews
SubcontractorsPrepare and submit shop drawings/data per schedule, respond to review comments, resubmit when required
Architect / EngineerReview submittals for design conformance, return with action stamp within contract timeframe
OwnerReview owner-furnished items, approve selections where required by contract

Step-by-Step Process

Phase 1: Submittal Schedule (Project Start)

Create the submittal schedule within the first 2 weeks of the project.

For each submittal, identify:

FieldDescriptionExample
Submittal numberSequential IDSUB-001
Spec sectionCSI specification section03 30 00 — Cast-in-Place Concrete
DescriptionWhat's being submittedConcrete mix designs (4000, 5000 PSI)
Responsible partySub or supplier who prepares itABC Concrete
Submit by dateWhen it must be submitted for review03/01/2026
Need by dateWhen approval is needed to maintain schedule04/01/2026
Lead timeFabrication/procurement time after approval2 weeks
Review timeContract-allowed review period14 calendar days

Schedule calculation (work backwards from need date):

Need-by date:           04/01/2026
- Lead time (2 weeks): 03/18/2026 ← Must be approved by this date
- Review time (14 days): 03/04/2026 ← Must be submitted by this date
- Preparation (1 week): 02/25/2026 ← Sub must start preparing
Front-Load Your Schedule

Submit everything you can in the first 30 days. Don't wait until you "need" it — architect review takes time, rejections take more time, and procurement has lead times. The earlier you submit, the more buffer you have.

Phase 2: Prepare the Submittal Package

Every submittal package includes:

  1. Transmittal cover sheet — Submittal number, spec section, description, date
  2. Shop drawings / product data — The actual submittal content
  3. Highlighted relevant sections — Don't make the reviewer hunt for what matters
  4. Deviations noted — If the product differs from spec, call it out explicitly
  5. Contractor review stamp — Your company's stamp indicating you've reviewed for compliance

Contractor review stamp options:

StampMeaning
ApprovedReviewed and complies with contract documents
Approved as NotedComplies with minor notes/clarifications
Revise and ResubmitDoes not comply — needs revision before A/E review
Always Review Before Submitting

Never forward a sub's submittal directly to the architect without reviewing it first. You're responsible for verifying it matches the contract documents. Sending garbage to the architect wastes everyone's time and makes you look unprofessional.

Phase 3: Submit to Architect/Engineer

  1. Log the submittal in the submittal log (date sent, to whom)
  2. Submit per contract requirements (electronically or hard copies as specified)
  3. Include all required copies (typically 1 electronic + specified hard copies)
  4. Note the contract review period (typically 10–14 calendar days)
  5. Set a follow-up reminder for the expected return date

Phase 4: Track Review Status

StatusDescriptionAction
SubmittedSent to reviewer, awaiting responseMonitor due date
Under ReviewAcknowledged by reviewerNo action needed
OverduePast contract review periodSend written follow-up, escalate
ReturnedResponse receivedProcess response (see Phase 5)

Follow-up schedule:

  • Day 7: Verify receipt if no acknowledgment
  • Day 10: Follow up if nearing review period deadline
  • Day 14+: Written notice that review is overdue, copy PM and owner

Phase 5: Process the Response

Architect/Engineer response stamps:

ActionMeaningWhat You Do
Approved / No Exceptions TakenProceed with fabrication/procurementOrder materials, distribute to sub
Approved as NotedProceed, but incorporate noted changesReview notes, confirm sub can comply, order
Revise and ResubmitDoes not comply — must be correctedReview comments, have sub revise, resubmit
RejectedFundamentally non-compliantStart over with compliant product/drawing
For Information OnlyNo action requiredFile for record

Phase 6: Resubmit (If Required)

  1. Review all comments with the subcontractor
  2. Sub revises and resubmits to you
  3. Verify corrections address all comments
  4. Resubmit with cover letter noting what was revised
  5. Track as a new submission with the same submittal number + revision (SUB-001 Rev 1)

Submittal Log

Maintain a running log of all submittals:

#SpecDescriptionSubDate SentDue BackDate ReturnedStatusNotes
SUB-00103 30 00Concrete mix designsABC Concrete02/1503/0102/27Approved
SUB-00205 12 00Structural steel shop dwgsDelta Steel02/1803/04Under ReviewFollow up 03/02
SUB-00308 11 00HM door framesBest Doors02/2003/0603/05Revise & ResubmitWrong gauge, see comments

Common Mistakes

MistakeConsequenceFix
No submittal scheduleSubmittals trickle in late, delay procurementCreate schedule in first 2 weeks, distribute to all subs
Submitting without contractor reviewRejections that could have been caught internallyAlways review and stamp before sending to A/E
Not tracking review periodsOverdue reviews go unnoticedLog every submittal, set reminders, follow up on day 10
Vague resubmittalsSame rejection happens againAddress every comment specifically, note what changed
Not distributing approvalsSub doesn't know they can orderDistribute approved submittals to sub within 24 hours
Lost submittals"We never received that" — delays and disputesUse transmittals with receipt confirmation for everything

Metrics

MetricTargetFrequency
Submittals on scheduleover 90% submitted by schedule dateWeekly
First-pass approval rateover 75%Monthly
Average review turnaroundWithin contract periodMonthly
Overdue submittalsZero overdue over 7 daysWeekly
Resubmittal turnaroundWithin 5 business daysPer occurrence

ResourceLink
Submittal Log TrackerSubmittal Log
Submittal GuideSubmittals Guide
Transmittal GeneratorGenerate Transmittal