⏱️ T&M Ticket Workflow Playbook

Capture time and material work as it happens. Get signatures same-day to avoid disputes. A T&M ticket without a signature is a donation.


Why T&M Ticket Management Matters

The One Rule That Matters

Get the signature the same day. Every day you wait, the chance of getting paid drops dramatically:

Signature TimingLikelihood of Payment
Same day~95%
Next day~75%
End of week~50%
Next month (with pay app)~25%
After the project~5%

When to Use T&M Tickets

SituationT&M Ticket?Notes
Owner/GC directs extra work, no agreed price yetYesTrack costs while negotiating the change order
Emergency work that can't wait for pricingYesDocument everything — negotiate later
Contract specifies T&M billing for certain workYesFollow contract T&M provisions exactly
Differing site conditions — extra effort requiredYesSupport your change order with actual cost data
Disputed scope — you believe it's extra workYesProtect yourself while the dispute is resolved
Work within your original contract scopeNoDon't T&M ticket your own contract work

Roles and Responsibilities

RoleResponsibilities
ForemanCreate T&M ticket in the field, document labor/equipment/materials in real-time, get daily signature
SuperintendentReview T&M tickets for accuracy, ensure signatures are obtained, submit to PM
Project ManagerVerify T&M tickets match written direction, compile for change order pricing or billing
GC / Owner RepresentativeReview and sign T&M tickets daily, confirm hours and resources

Step-by-Step Process

Step 1: Get Written Direction First

Before starting any T&M work:

  1. Receive written direction — Email, RFI response, field directive, or COR
  2. If direction is verbal — Confirm in writing immediately:

"Per our conversation at 9:30 AM today, you directed us to [description of work]. We will track this work on T&M tickets pending a change order. Please confirm."

  1. Reference the direction on every T&M ticket — "Per field directive FD-007 dated 02/12/2026"
No Written Direction = No Payment

If you can't point to written direction for the extra work, you have no basis for billing. Get it in writing before you start, or confirm verbal direction in writing within hours.

Step 2: Create the T&M Ticket

Start a new T&M ticket at the beginning of each day the extra work is performed.

Header information:

FieldDetails
T&M Ticket #Sequential number (TM-001, TM-002, etc.)
DateToday's date
ProjectProject name and number
ReferenceField directive, RFI, or COR number
Description of workSpecific description of extra work being performed
LocationWhere on the project
WeatherConditions that may affect work

Step 3: Document Labor in Real-Time

Track as the day progresses — not from memory at the end of the day.

Worker NameTrade / ClassificationStart TimeEnd TimeTotal HoursRateAmount
Mike JohnsonCarpenter7:00 AM3:30 PM8.0 hrs$85/hr$680
Tony ReevesCarpenter7:00 AM3:30 PM8.0 hrs$85/hr$680
Dave ChenLaborer7:00 AM12:00 PM4.5 hrs$62/hr$279
Labor Subtotal$1,639

Labor rate includes:

  • Base wage
  • Burden (taxes, insurance, benefits) — per contract markup provisions
  • Small tools allowance (if applicable per contract)

Step 4: Document Equipment

EquipmentID/SizeStart TimeEnd TimeTotal HoursRateAmount
CAT 320 ExcavatorEXC-037:00 AM2:00 PM7.0 hrs$175/hr$1,225
Compactor (plate)10:00 AM2:00 PM4.0 hrs$25/hr$100
Equipment Subtotal$1,325

Equipment rates:

  • Use contract-specified rates, or
  • Rental rate equivalents (Blue Book, FEMA, or actual rental invoices)
  • Include operator separately in labor section (don't double-count)

Step 5: Document Materials

MaterialQuantityUnitUnit CostAmountInvoice #
6" DIP Pipe40LF$28.50$1,140INV-44821
6" MJ Fittings4EA$85.00$340INV-44821
Crushed Rock (3/4")8Tons$42.00$336DEL-2208
Materials Subtotal$1,816

Keep all receipts, invoices, and delivery tickets — attach copies to the T&M ticket.

Step 6: Calculate Totals

CategoryAmount
Labor$1,639
Equipment$1,325
Materials$1,816
Direct Cost Subtotal$4,780
Overhead (15% per contract)$717
Profit (10% per contract)$478
Daily Total$5,975

Use your contract markup rates. Common markups:

  • Overhead: 10–15% on own work; 5–10% on sub work
  • Profit: 5–10% on own work; 5% on sub work
  • Bond premium: 1–2% (if bonded)

Step 7: Get the Signature — TODAY

At end of shift (or during the work if GC/owner is available):

  1. Present the completed T&M ticket to the GC or owner representative
  2. Walk them through the labor, equipment, and materials listed
  3. Ask them to review and sign
  4. If they agree — signature, date, and printed name
  5. If they dispute an item — discuss it, note the dispute on the ticket, get signature for the undisputed portion
  6. Give them a copy and keep the original

What if they refuse to sign?

  1. Note "Signature requested and refused" on the ticket
  2. Record the name of the person who refused and the date/time
  3. Send the T&M ticket via email or certified mail the same day
  4. Continue tracking on subsequent days
  5. Escalate to the PM for contractual remedies

Step 8: Submit and Track

  1. Submit copies to your PM and project file same day
  2. Compile T&M tickets with the associated change order or pay application
  3. Track cumulative T&M costs by directive/change order
  4. Include in monthly pay app with all backup documentation

T&M Ticket Best Practices

PracticeWhy
One ticket per dayEasier to sign daily, keeps records current
New ticket for each directiveDon't mix different extra work on one ticket
Include description of work"Rock removal at Grid B/4 per FD-007" — not just hours and costs
Photo documentationPhotograph the work being done, conditions, equipment in use
Track waiting/standby timeIf your crew is idle due to the change, that's billable time
Separate T&M from contract workDon't mix base contract work with T&M on the same ticket
Keep originalsNever give up your only copy — provide copies to the GC/owner

Common Mistakes

MistakeConsequenceFix
No same-day signature"We didn't have 3 guys there that day" — disputedSign every ticket, every day, no exceptions
Reconstructing from memoryInaccurate, looks fabricatedFill out the ticket in real-time during the work
No written direction"We never told you to do that"Get written direction before starting, or confirm verbally in writing
Missing material receiptsCan't prove material costsKeep every receipt and attach to the ticket
Using wrong markup ratesDisputed, rejected, or underpaidKnow your contract markups before the first ticket
Waiting to submit with pay appMonths of unsigned tickets — good luck collectingSubmit and get signatures daily
Mixing base contract and T&MGC argues "that's in your scope"Separate tickets, separate cost codes, clear descriptions

Metrics

MetricTargetFrequency
T&M tickets signed same day100%Daily
Written direction on file100% of T&M workPer directive
T&M submitted with pay app100% of outstanding ticketsMonthly
T&M collection rateover 90%Monthly
Average time from T&M to COunder 30 daysPer directive

ResourceLink
T&M GuideTime & Materials Guide
Change Order PlaybookChange Order Workflow
Daily Report PlaybookField Reporting
Markup CalculatorCalculate Markup
Change Order Markup CalculatorCO Markup