๐Ÿ“… Project Duration Calculator

Estimate project duration based on work scope, crew size, and productivity rates.


Quick Formulaโ€‹

Basic Durationโ€‹

Duration = Total Work รท (Crew Size ร— Hours per Day ร— Productivity Rate ร— Working Days per Week)

With Bufferโ€‹

Duration with Buffer = Base Duration ร— (1 + Contingency Factor)

Common Duration Factorsโ€‹

Weather Daysโ€‹

ClimateWeather Days per Month
Mild1-2 days
Moderate2-3 days
Severe3-5 days

Working Daysโ€‹

Working Days = Calendar Days - Weekends - Holidays - Weather Days

Common Calculationsโ€‹

Example 1: Simple Projectโ€‹

Work: 5,000 sq ft framing Crew: 4 workers Productivity: 75 sq ft/hr per worker Hours: 8 hours/day Working days: 5 days/week

Calculation:

  • Daily output: 4 ร— 8 ร— 75 = 2,400 sq ft/day
  • Days needed: 5,000 รท 2,400 = 2.08 days
  • With 20% buffer: 2.08 ร— 1.20 = 2.5 days (3 days)

Example 2: Complex Projectโ€‹

Work: Multiple trades, 10,000 sq ft building Crews: Various (concrete, framing, MEP, finishes) Schedule: Sequential phases

Phases:

  • Site work: 2 weeks
  • Foundation: 2 weeks
  • Framing: 4 weeks
  • MEP: 3 weeks
  • Finishes: 4 weeks
  • Total: 15 weeks

Contingency Factorsโ€‹

Project TypeContingency
Simple, repetitive10-15%
Standard15-20%
Complex20-30%
High-risk30-40%


Plan for Delays

Always add contingency to duration estimates. Weather, material delays, and unforeseen conditions are common.