๐ท Crew Productivity Calculator
Calculate crew productivity, daily output, and labor hours needed for construction tasks.
Quick Formulaโ
Daily Outputโ
Daily Output = Crew Size ร Hours per Day ร Productivity Rate
Labor Hours Neededโ
Labor Hours = Total Work รท Daily Output
Crew Days Neededโ
Crew Days = Labor Hours รท (Crew Size ร Hours per Day)
Common Productivity Ratesโ
Concrete Workโ
| Task | Rate | Unit |
|---|---|---|
| Formwork | 15-25 sq ft/hr | Per worker |
| Rebar | 100-200 lbs/hr | Per worker |
| Pour/finish | 20-40 sq ft/hr | Per worker |
Framingโ
| Task | Rate | Unit |
|---|---|---|
| Wall framing | 50-100 sq ft/hr | Per worker |
| Roof framing | 30-60 sq ft/hr | Per worker |
| Sheathing | 100-150 sq ft/hr | Per worker |
Drywallโ
| Task | Rate | Unit |
|---|---|---|
| Hanging | 100-150 sq ft/hr | Per worker |
| Taping | 200-300 sq ft/hr | Per worker |
| Finishing | 150-250 sq ft/hr | Per worker |
Common Calculationsโ
Example 1: Concrete Slabโ
Work: 1,000 sq ft slab Crew: 3 workers Hours: 8 hours/day Productivity: 25 sq ft/hr per worker
Calculation:
- Daily output: 3 ร 8 ร 25 = 600 sq ft/day
- Days needed: 1,000 รท 600 = 1.67 days (2 days)
Example 2: Framingโ
Work: 2,000 sq ft wall framing Crew: 4 workers Hours: 8 hours/day Productivity: 75 sq ft/hr per worker
Calculation:
- Daily output: 4 ร 8 ร 75 = 2,400 sq ft/day
- Days needed: 2,000 รท 2,400 = 0.83 days (under 1 day)
Factors Affecting Productivityโ
| Factor | Impact | Adjustment |
|---|---|---|
| Weather | -10% to -30% | Bad weather slows work |
| Complexity | -20% to -40% | Complex work slower |
| Experience | +10% to +30% | Experienced crews faster |
| Site conditions | -10% to -20% | Poor conditions slow work |
Related Resourcesโ
- Labor Burden Calculator - True cost of labor
- Overtime Calculator - Calculate OT costs
Track Actual Productivity
Compare estimated vs. actual productivity to improve future estimates. Track by task, crew, and conditions.