Skip to main content
Skip to main content

💰 Cash Flow Projection Calculator

Project cash flow for construction projects and your entire company. Essential for financial planning and avoiding cash crunches.

Why Cash Flow Projections Matter

Construction is cash-intensive. You pay for materials and labor before you get paid. Cash flow projections help you:

  • Avoid cash crunches - Know when you'll need money
  • Plan financing - Line up credit before you need it
  • Make decisions - Can you take on that new project?
  • Manage payments - Prioritize who gets paid when
Cash Flow Kills More Contractors Than Profitability

Many profitable contractors fail because they run out of cash. Track it religiously.

How Construction Cash Flow Works

The Cash Flow Cycle

Pay for Materials/Labor → Wait for Payment → Receive Payment → Pay Next Cycle
(Week 1-4) (Week 5-8) (Week 9-12)

Typical Timeline:

  • Week 1-4: Pay for work performed
  • Week 5-8: Wait for owner payment
  • Week 9-12: Receive payment (if approved on time)

The Problem

You're always paying for work before you get paid. This creates negative cash flow that must be funded.

Project Cash Flow Projection

Step 1: Project Schedule

Break your project into phases and estimate:

  • Start date for each phase
  • Duration of each phase
  • Completion date

Step 2: Estimate Costs by Period

For each period (week/month), estimate:

  • Direct Costs: Labor, materials, equipment, subcontractors
  • Indirect Costs: General conditions, overhead allocation
  • Total Costs: Sum of direct and indirect

Step 3: Estimate Revenue by Period

For each period, estimate:

  • Work Completed: % complete × contract value
  • Retention: Typically 5-10% withheld
  • Net Revenue: Work completed - retention

Step 4: Calculate Cash Flow

Cash Flow = Revenue Received - Costs Paid

Timing Matters:

  • Costs paid: When you pay (typically weekly/bi-weekly)
  • Revenue received: When owner pays (typically 30-60 days after invoice)

Step 5: Calculate Cumulative Cash Flow

Cumulative Cash Flow = Previous Cumulative + Current Period Cash Flow

Interactive Calculator

Interactive calculator component coming soon

For now, use this process:

Monthly Cash Flow Projection

MonthCosts PaidRevenue ReceivedNet Cash FlowCumulative
Month 1$_______$_______$_______$_______
Month 2$_______$_______$_______$_______
Month 3$_______$_______$_______$_______
Month 4$_______$_______$_______$_______
Month 5$_______$_______$_______$_______
Month 6$_______$_______$_______$_______

Key Metrics

  • Peak Negative Cash Flow: $_______ (lowest point)
  • Breakeven Point: Month _______
  • Total Cash Needed: $_______
  • Payback Period: _______ months

Company-Wide Cash Flow

Step 1: List All Projects

For each active project:

  • Project name
  • Contract value
  • % complete
  • Costs to date
  • Billed to date
  • Received to date

Step 2: Estimate Monthly Costs

  • Project Costs: Sum of all project costs
  • Overhead Costs: Office, admin, non-project costs
  • Debt Service: Loan payments
  • Other: Taxes, distributions, etc.

Step 3: Estimate Monthly Revenue

  • Project Payments: Expected payments from projects
  • Other Income: Equipment rental, etc.

Step 4: Calculate Net Cash Flow

Net Cash Flow = Total Revenue - Total Costs

Common Cash Flow Scenarios

Scenario 1: Growing Company

  • Taking on more work
  • Cash needs increase faster than revenue
  • Solution: Line of credit, retain earnings, slow growth

Scenario 2: Slow Payment

  • Owner pays late
  • Cash gap widens
  • Solution: Invoice promptly, follow up, consider financing

Scenario 3: Front-Loaded Project

  • Early payments cover costs
  • Positive cash flow early
  • Risk: Must finish project to collect remaining

Scenario 4: Back-Loaded Project

  • Most payment at end
  • Negative cash flow throughout
  • Risk: Need significant working capital

Improving Cash Flow

  1. Invoice Promptly - Don't delay billing
  2. Follow Up - Stay on top of receivables
  3. Negotiate Terms - Better payment terms
  4. Front-Load SOV - More payment early (ethically)
  5. Reduce Retention - Negotiate lower retention
  6. Line of Credit - Have credit available
  7. Retain Earnings - Build working capital
  8. Manage Payables - Pay on time but not early

Red Flags

Watch for these warning signs:

  • Cumulative cash flow stays negative
  • Peak negative exceeds available credit
  • Multiple projects all negative at once
  • Receivables aging beyond 60 days
  • Can't pay bills on time