⏰ Delay Claims
Delays happen on almost every project. Recovering your costs depends on proper documentation and understanding your contractual rights.
Document delays in real-time. Trying to reconstruct a delay claim after the fact rarely succeeds.
Types of Delays
Excusable vs. Non-Excusable
Excusable delays - Not your fault
- Owner-caused delays
- Design errors
- Unforeseen conditions
- Weather (if beyond normal)
- Force majeure
Non-excusable delays - Your fault
- Poor planning
- Insufficient manpower
- Equipment breakdowns
- Subcontractor failures
Compensable vs. Non-Compensable
Compensable - You get time AND money
- Owner-directed changes
- Design issues
- Owner-caused suspension
- Differing site conditions
Non-compensable - You get time only (maybe)
- Weather delays
- Force majeure
- Delays by other contractors (often)
Concurrent Delays
When multiple delays happen at the same time:
- One excusable, one not
- Both parties contributed
- Complex to analyze
- Usually = time only, no damages
Contract Provisions to Know
No Damages for Delay Clauses
Common language:
"Contractor shall not be entitled to any damages for delay, regardless of cause."
What it means:
- You may get time extension
- But no additional compensation
- Very owner-favorable
Exceptions often carved out:
- Active interference
- Bad faith
- Abandonment
- Gross negligence
Notice Requirements
Typical requirement:
"Contractor must provide written notice of delay within 5 days of becoming aware."
Critical: Miss the notice deadline, lose your claim.
Time Extension Procedures
Know your contract:
- How to request extension
- What documentation needed
- Who approves
- Timeline for decision
Documenting Delays
Real-Time Documentation
Daily reports should note:
- Weather conditions
- Work accomplished
- Work delayed and why
- Instructions received
- Lack of access/information
- Equipment issues
- Manpower levels
Critical to document:
- Date delay began
- Cause of delay
- Impact to schedule
- Verbal instructions (follow up in writing)
- Photos of conditions
Contemporaneous Records
Credible documentation:
- Created at the time
- By people with knowledge
- In normal course of business
- Consistent format
Less credible:
- Created after the fact
- Reconstructed from memory
- Inconsistent with other records
- Only when dispute arose
What to Capture
For each delay event:
- Date identified
- Cause (specific and detailed)
- Responsibility (owner, designer, other)
- Activities affected
- Duration of impact
- Costs incurred
- Notice sent (date and method)
- Response received
Calculating Delay Damages
Extended General Conditions
Costs that continue for longer duration:
- Site supervision
- Field office
- Temporary facilities
- Equipment rental
- Insurance
- Utilities
Calculate:
Monthly General Conditions: $25,000
Delay Period: 3 months
Extended GC Claim: $75,000
Labor Inefficiency
Delays can cause:
- Stacking of trades
- Out-of-sequence work
- Multiple mobilizations
- Learning curve loss
Methods to calculate:
- Measured mile (compare productive vs. impacted)
- Industry studies
- Total cost (last resort)
Material Escalation
If delay pushes work into period of price increases:
- Steel price increase
- Fuel cost increase
- Lumber price increase
Document: Original quote date vs. actual purchase date
Equipment Costs
- Owned equipment: Calculate daily/monthly rate
- Rented equipment: Actual rental cost
- Standby costs (if equipment sitting idle)
Home Office Overhead
Eichleay Formula (federal contracts):
Daily Rate = (Contract Billings / Total Billings) ×
(Total Overhead / Days of Contract)
Overhead Claim = Daily Rate × Days of Delay
Presenting a Delay Claim
Claim Contents
-
Executive Summary
- Amount claimed
- Brief description
- Contract basis
-
Facts
- Project background
- Chronology of delays
- Cause identification
-
Contract Analysis
- Relevant provisions
- Notice compliance
- Entitlement basis
-
Schedule Analysis
- Critical path impact
- As-planned vs. as-built
- Delay responsibility
-
Damages Calculation
- Detailed cost breakdown
- Supporting documentation
- Summary
-
Supporting Documents
- Notices sent
- Correspondence
- Daily reports
- Photos
- Cost backup
Schedule Analysis Methods
As-Planned vs. As-Built
- Compare original to actual schedule
- Identify where delays occurred
- Simple but doesn't show causation
Impacted As-Planned
- Insert delay events into baseline
- Show theoretical impact
- Forward-looking
Collapsed As-Built
- Start with as-built schedule
- Remove delay events
- "But for" analysis
Windows Analysis
- Analyze schedule in time periods
- Most accurate for complex delays
- More expensive to prepare
Common Mistakes
1. Missing Notice Requirements
Problem: Claim waived due to late notice Solution: Know deadlines, send notice immediately
2. Poor Documentation
Problem: Can't prove delay occurred Solution: Document daily, in real-time
3. No Schedule Analysis
Problem: Can't show critical path impact Solution: Maintain updated schedule, analyze delays
4. Ignoring Concurrent Delays
Problem: Claiming damages when you also delayed Solution: Honestly assess concurrent delays
5. Inflated Claims
Problem: Lose credibility Solution: Claim only what you can prove
Defending Against Delay Claims
If You Receive a Claim
- Review notice compliance - Was it timely?
- Analyze causation - Did claimed events cause delay?
- Check critical path - Was work on critical path?
- Identify concurrency - Were there concurrent delays?
- Review documentation - Does evidence support claim?
- Calculate damages - Are costs reasonable and proven?
Common Defenses
- Late or no notice
- Delay not on critical path
- Concurrent delay
- No proof of causation
- Damages not documented
- "No damages for delay" clause