๐ฐ Pay Application Guide
Pay applications are how you get paid. Master the process to improve cash flow and avoid disputes.
Submit on time, every time. A late pay app means you wait another 30+ days to get paid.
Understanding Pay Applicationsโ
A pay application (or "pay app") is your formal request for payment based on work completed. Most commercial projects use AIA G702/G703 forms.
Key Documentsโ
| Document | Purpose |
|---|---|
| AIA G702 | Application and Certificate for Payment (summary) |
| AIA G703 | Continuation Sheet (schedule of values detail) |
| Lien Waivers | Required releases for payment |
| Supporting Docs | Backup for stored materials, change orders, etc. |
The Pay Application Processโ
1. Set Up Schedule of Values (SOV)โ
Before your first pay app, establish your SOV:
- Break down contract into logical line items
- Front-load moderately (but don't be obvious)
- Include mobilization, general conditions, closeout
- Get owner/architect approval before first billing
SOV Tips:
- 15-30 line items for most projects
- Match specification divisions where possible
- Include stored materials line if needed
- Build in room for change orders
2. Monthly Progress Assessmentโ
Around the 25th of each month:
- Walk the project with your team
- Assess percent complete by line item
- Document with photos
- Calculate earned value
3. Prepare the Applicationโ
AIA G702 includes:
- Original contract sum
- Approved change orders to date
- Total completed and stored
- Retainage
- Current payment due
AIA G703 shows:
- Each SOV line item
- Previous billings
- Current period work
- Stored materials
- Balance to finish
4. Gather Required Documentsโ
Most contracts require:
- โ Signed pay application
- โ Conditional lien waiver (current)
- โ Unconditional lien waiver (previous)
- โ Sub conditional waivers
- โ Certified payroll (if prevailing wage)
- โ Insurance certificates (if expiring)
- โ Stored material documentation
5. Submit on Timeโ
Critical: Know your contract's billing deadline. Miss it by a day and you wait another month.
Common deadlines:
- 25th of the month
- Last day of the month
- 5 days before owner's pay app due
6. Follow Upโ
Track your pay app through:
- Architect review (7-10 days)
- Owner approval (7-10 days)
- Payment processing (15-30 days)
If payment is late: Send written notice per contract terms.
Common Pay App Mistakesโ
Overbillingโ
Billing more than you've completed:
- โ Damages trust with owner/architect
- โ Creates problems at closeout
- โ Can be considered fraud
Underbillingโ
Billing less than you've completed:
- โ Hurts your cash flow
- โ Increases risk if project goes bad
- โ Makes it hard to catch up later
Missing the Deadlineโ
- โ Wait 30+ more days for payment
- โ Cash flow crisis
- โ Hard to explain to your bank
Incomplete Packagesโ
Missing lien waivers or backup:
- โ Pay app rejected, resubmit
- โ Delays payment cycle
- โ Makes you look disorganized
Retentionโ
Most contracts hold 5-10% retention:
- Standard: 10% until 50% complete, then 5%
- Reduced: Some contracts allow 5% from start
- Release: Typically at substantial completion
Getting Retention Releasedโ
- Achieve substantial completion
- Complete punch list
- Submit all closeout documents
- Request retention release in writing
- Provide final lien waivers
Stored Materialsโ
Billing for materials stored off-site:
Requirements:
- Material is fabricated or non-returnable
- Stored in bonded warehouse or secured area
- Proof of ownership (invoices)
- Insurance certificate covering storage
- Some contracts prohibit off-site storage billing
Disputed Amountsโ
If the owner disputes a line item:
- Don't hold up the whole pay app โ Bill undisputed amounts
- Document your position โ Respond in writing
- Continue working โ Unless contract allows suspension
- Escalate if needed โ Per dispute resolution clause
Progress Tracking Tipsโ
Percent Complete Methodsโ
| Method | Best For |
|---|---|
| Units installed | Repetitive work (doors, fixtures) |
| Linear feet | Pipe, conduit, ductwork |
| Square feet | Drywall, flooring, roofing |
| Earned hours | Labor-heavy work |
| Milestone | Long-lead items |
Weekly Trackingโ
Don't wait until billing time:
- Track progress weekly
- Update quantities in real-time
- Take progress photos
- Note any delays or issues
Tools & Resourcesโ
Free Template: Download our schedule of values template and pay app checklist.
Digital Option: BLDR Pro can track progress by cost code, generate SOV reports, and send billing deadline reminders.