Skip to main content
Skip to main content

๐Ÿ’ฐ Pay Application Guide

Pay applications are how you get paid. Master the process to improve cash flow and avoid disputes.

Cash Flow is King

Submit on time, every time. A late pay app means you wait another 30+ days to get paid.

Pay application lifecycle
1
Set up schedule of values
Break the contract into line items with allocated values. Front-loading is risky โ€” keep it reasonable and defensible.
2
Compile backup documentation
Gather daily reports, delivery tickets, sub invoices, stored material documentation, and change order approvals.
3
Complete and submit pay app
Fill out the AIA G702/G703 or owner's required form. Submit on the contractual due date โ€” not a day late.
4
Track approval and payment
Follow up on approval status. If disputed, respond immediately. Track the payment through to receipt.
5
Manage retainage
Track retainage separately. Submit release requests at substantial completion per contract terms.

Understanding Pay Applicationsโ€‹

A pay application (or "pay app") is your formal request for payment based on work completed. Most commercial projects use AIA G702/G703 forms.

Key Documentsโ€‹

DocumentPurpose
AIA G702Application and Certificate for Payment (summary)
AIA G703Continuation Sheet (schedule of values detail)
Lien WaiversRequired releases for payment
Supporting DocsBackup for stored materials, change orders, etc.

The Pay Application Processโ€‹

1. Set Up Schedule of Values (SOV)โ€‹

Before your first pay app, establish your SOV:

  • Break down contract into logical line items
  • Front-load moderately (but don't be obvious)
  • Include mobilization, general conditions, closeout
  • Get owner/architect approval before first billing

SOV Tips:

  • 15-30 line items for most projects
  • Match specification divisions where possible
  • Include stored materials line if needed
  • Build in room for change orders

2. Monthly Progress Assessmentโ€‹

Around the 25th of each month:

  1. Walk the project with your team
  2. Assess percent complete by line item
  3. Document with photos
  4. Calculate earned value

3. Prepare the Applicationโ€‹

AIA G702 includes:

  • Original contract sum
  • Approved change orders to date
  • Total completed and stored
  • Retainage
  • Current payment due

AIA G703 shows:

  • Each SOV line item
  • Previous billings
  • Current period work
  • Stored materials
  • Balance to finish

4. Gather Required Documentsโ€‹

Most contracts require:

  • โœ… Signed pay application
  • โœ… Conditional lien waiver (current)
  • โœ… Unconditional lien waiver (previous)
  • โœ… Sub conditional waivers
  • โœ… Certified payroll (if prevailing wage)
  • โœ… Insurance certificates (if expiring)
  • โœ… Stored material documentation

5. Submit on Timeโ€‹

Critical: Know your contract's billing deadline. Miss it by a day and you wait another month.

Common deadlines:

  • 25th of the month
  • Last day of the month
  • 5 days before owner's pay app due

6. Follow Upโ€‹

Track your pay app through:

  • Architect review (7-10 days)
  • Owner approval (7-10 days)
  • Payment processing (15-30 days)

If payment is late: Send written notice per contract terms.

Common Pay App Mistakesโ€‹

Overbillingโ€‹

Billing more than you've completed:

  • โŒ Damages trust with owner/architect
  • โŒ Creates problems at closeout
  • โŒ Can be considered fraud

Underbillingโ€‹

Billing less than you've completed:

  • โŒ Hurts your cash flow
  • โŒ Increases risk if project goes bad
  • โŒ Makes it hard to catch up later

Missing the Deadlineโ€‹

  • โŒ Wait 30+ more days for payment
  • โŒ Cash flow crisis
  • โŒ Hard to explain to your bank

Incomplete Packagesโ€‹

Missing lien waivers or backup:

  • โŒ Pay app rejected, resubmit
  • โŒ Delays payment cycle
  • โŒ Makes you look disorganized

Retentionโ€‹

Most contracts hold 5-10% retention:

  • Standard: 10% until 50% complete, then 5%
  • Reduced: Some contracts allow 5% from start
  • Release: Typically at substantial completion

Getting Retention Releasedโ€‹

  1. Achieve substantial completion
  2. Complete punch list
  3. Submit all closeout documents
  4. Request retention release in writing
  5. Provide final lien waivers

Stored Materialsโ€‹

Billing for materials stored off-site:

Requirements:

  • Material is fabricated or non-returnable
  • Stored in bonded warehouse or secured area
  • Proof of ownership (invoices)
  • Insurance certificate covering storage
  • Some contracts prohibit off-site storage billing

Disputed Amountsโ€‹

If the owner disputes a line item:

  1. Don't hold up the whole pay app โ€” Bill undisputed amounts
  2. Document your position โ€” Respond in writing
  3. Continue working โ€” Unless contract allows suspension
  4. Escalate if needed โ€” Per dispute resolution clause

Progress Tracking Tipsโ€‹

Percent Complete Methodsโ€‹

MethodBest For
Units installedRepetitive work (doors, fixtures)
Linear feetPipe, conduit, ductwork
Square feetDrywall, flooring, roofing
Earned hoursLabor-heavy work
MilestoneLong-lead items

Weekly Trackingโ€‹

Don't wait until billing time:

  • Track progress weekly
  • Update quantities in real-time
  • Take progress photos
  • Note any delays or issues

Tools & Resourcesโ€‹

Free Template: Download our schedule of values template and pay app checklist.

Digital Option: BLDR Pro can track progress by cost code, generate SOV reports, and send billing deadline reminders.

Was this page helpful?